1986-64 Authorizing Execution of Contract Amendment #15 with URS Co. for Construction Services for Water and Sewer Improvements in Service District #1.KODIAK ISLAND BOROUGH
RESOLUTION NO. 86-64-R
A RESOLUTION OF THE KODIAK ISLAND BOROUGH ASSEMBLY
AUTHORIZING APPROVAL OF CONTRACT AMENDMENT NO. 15 WITH URS COMPANY?
FOR CONSTRUCTION SERVICES FOR WATER AND SEWER IMPROVEMENTS IN
SERVICE DISTRICT NO. 1.
WHEREAS, the Kodiak Island Borough by Resolution No. 82-13-R approved a
contract with URS Company for design of water and sewer improvements in Service
District No. 1; and
WHEREAS, the sixth project is scheduled for award on October 2, 1986; and
WHEREAS, the Kodiak Island Borough desires to have URS Company continue
with project administration tbrough the construction phase;
NOW, THEREFORE, BE IT RESOLVED by the Kodiak Island Borough Assembly
that Amendment No. 15 for provision of construction services by URS Company is
approved with costs and fixed fee not to exceed the following:
Amendment No. 15:
Cost $345,283
Fixed Fee 42,725
Total $388,008
BE IT FURTHER RESOLVED that the above expenditures are hereby authorized
from funds received for the Island Lake Water and Sewer Project and that the Borough
Mayor is hereby authorized and instructed to execute the appropriate documents.
PASSED AND APPROVED this _ day of , 1986
by the Kodiak Island Borough Assembly.
ATTEST:
Bororro Clerk
KODIAK ISLAND BOROUGH
Borough Mayor
K ui
Presiding Officer
SUMMARY OF EXPENSES
ASSOCIATED WITH CONSTRUCTION ADMINISTRATION SERVICES
SERVICE DISTRICT NO. 1 WATER AND SEWER IMPROVEMENTS
PROJECT NO. 85-2
August 27, 1986
I, WORK TO BE COMPLETED BY URS COMPANY
Task No. and Description
Cost
Amendment 15
I. Provide assistance through bid
ug period: tabulate, review, and
Project 85-2
analyze bids received, and assist the Borough in obtaining
signed contract.
$ 5,960
2. Provide project management and coordinate with the Borough
and regulatory agencies during construction
62,599
3. Review shop drawings, construction drawings, and other submittals
ubmi-
made by the Contractor for compliance with the design s
cations. Review laboratory and shop test reports of materials and
equipment. Prepare supplementary sketches to adjust to field
conditions not anticipated during design.
11,626
4. Provide resident construction manager (project representative)
and field assistant commensurate with the extent of construction
activity in progress.
154,648
5. Prepare monthly construction progress reports, contractar's
periodical pay estimates, change orders, and other items necessary
for the orderly progress of the work.
41,787
6. Provide field inspection by design team as needed, make final field
observation, and prepare O & M manual for completed project.
11,925
7. Coordinate the taking of pre -construction video tape records
between the Contractor and the Borough. Video taping and all
necessary equipment to be furnished by the Borough with
assistance by the Contractor
1,749
S. Coordinate instrument field layout for construction in accordance
with scope of survey work to be.performed under this project.
7,617
9. Prepare one set of reproducible construction revised to
plans
conform with construction records for the Borough's use and files.
11,507
10. Maintain field inspection office, files, and inspection records
for the work performed.
36,216
11. Provide instrument field location for points of intersection of
the sewer line, manhole locations, water line locations, alignment
stakes, and run level loops to provide elevation beach marks.
42,372
12. Coordinate final design alignment for field layout, balance level
loops, provide office computations, and coordinate field layout
with crew during the progress of the work including the
establishment and maintaining of survey records.
3.107
Total
$ 388.008
IL EXPENSES INCLUDED IN TOTAL COST
I. Travel, housing, per diem, mileage, etc. $ 38, 212
2. AL other expenses, including printing, office neat, eta 22,237
Total S 60,449
III. COST SUMMARY - URS COMPANY
1. Administration, coordination, etc. $ 345,283
2. Profit at 12.4 percent 42,725
TOTAL COST NOT TO EXCEED $ 388,008