SUBJECT: Change Order No. 8 Amending Contract FY2019-10 Architectural and
Engineering Services Term Contract for Design for the Borough Building Boiler
Room Renovation
ORIGINATOR: Matt Gandel
RECOMMENDATION:
Authorize the Manager to Execute Change Order No. 8 Amending Contract FY2019-10 with Jensen
Yorba Wall, Inc. for Architectural and Engineering Services Term Contract in an amount not to exceed
$22,004.
DISCUSSION:
Kodiak Island Borough Code 3.30.100 Change Orders - Manager Authority stales that a change order
greater than five percent of approved contract amount or $50,000, whichever is lower, requires
Assembly approval.
At the regular meeting on March 5, 2020, the Assembly approved Change Order No. 7 amending
Contract FY2019-10 for initial design efforts to replace the boilers at the Borough Building, including a
hazardous material survey. Prior to the meeting staff provided the Assembly with an additional cost to
evaluate the feasibility of replacing the boilers at the Maintenance Building as well, and possibly
connecting both buildings for increased efficiency for the heating systems of both buildings. While the
alternate proposal was discussed by the Assembly the motion that was voted on was not amended to
include the cost. This change order is to approve the alternate cost previously discussed but not
officially approved.
ALTERNATIVES:
FISCAL IMPACT:
The Assembly approved using $50,000 in Fund 469 Renewal and Replacement funds for design work
for this project as part of Ordinance No. 2020-01 A. There is adequate funding to complete these initial
design efforts.
OTHER INFORMATION:
Kodiak Island Borough
Page 2 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
AGENDA ITEM #3.A.
KODIAK ISLAND BOROUGH TERM CONTRACT CHANGE ORDER
710 MILL BAY ROAD Project Name: Project Number:
KODIAK, ALASKA 99615 Borough Building Boiler Replacement 469-614452.140 20005.4
Contractor: Jensen Yorba Wall, Inc.
Cast
Term Contract No.: 2019-10
Change Order No.: 08
Original Project Budget:
$ 50,000.00
Original Contract:
$
0.00
Previous Budget Changes:
$ 0.00
Previous Changes:
S
260,756.00
Adjusted Project Budget:
$ 0.00
This Change:
$
22,004.00
To -Date Project Expenses:
$ 174.00
% of Original Contract
>5%
To -Date Project Encumbrances:
$ 0.00
Adjusted Contract:
S
322,527.00
Current Remaining Project Budget:
$ 49,826.00
Description of Change
Cast
Evaluate feasibility of replacing boilers in the Maintenance Building and connecting the two buildings
S 22,004.00
together, including additional mechanical and electrical engineering and harmer survey per the
proposal dated March 4, 2020, to be charged on a time and materials basis.
The time provided for completion of the contract is (® unchanged) (D increased) (Ddecreased) by 0 calendar days. This document
shall become an amendment to the contract and all provisions of the contract will apply thereto.
Per Borough Cade 3.30.100, a change order that does not exceed five percent of the original contract amount or $50,000,
whichever is lover, requires approval by the mayor and deputy presiding officer, the mayor and one assembly member in the
absence of the deputy presiding office, or the deputy presiding officer and one assembly member in the absence of the mayor.
Change orders grealerthan rive percent ofaooroved contract amount or $50.000. whichever is lower, require assembly approval.
Accepted By:
Contractor's Representative
Recommended: Date: Date:
Approved By:
Engineering/Facilities Director Finance Director
Date: Anent:
Borough Manager Borough Clerk
Mayor and Deputy Presiding Officer Approval (does not exceeditve percent ofthe ortgmal mntrocr amount or 150,000, whichever is lower)
Approved By: Date: Date:
Borough Mayor Deputy Presiding Officer
Borough Assembly Approval (greater thou Jivepercent ofappmved contracramount or $50,000, whichever Is lower)
Approved By: Date: Attest:
Borough Manager Borough Clerk
Revived 09119
Date:
Pnpe I of 1
Page 3 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
AGENDA ITEM O.A.
Page 4 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
s
N
.■■■
0 0 0 0 0 0 0 0
Vl Vf O N tR V! Vl Vf
M
Q
g
MEMO
■■■O
o
w
N
Xa
0 0 0 0 0 0 0 0
N N N N N N h N
F-
u
m
o o a o 0 0 0 0
a
W
VF Vf
d
Z
NIr
d
W
6
�
N
W
d
O
�
m
N
m
a_
E E d E E E
d
�
O. O. 6
LL
x
E E E E
E E w E E E w w
rn
'o
E E E
m
`0
F H
v
m
A
9
C
d
W
0 0 0 0 0 0 0 0
W
N N O l H N N N{ A
O
y
LL
p
y
d
lD
L
D
rl
N
o
i
Y
H
U
❑
C m
wl
°J o
a
C
J
Oa
✓ c O
C O u
m
i
c E .� 'E Z
S
d 0 d
E a
u o
a
m o
m
> > Z
cc
dd c Z c c
'm
vWUi
z m z u
z°
d d
i
❑ Q E CO u C u u
Q
O
Fn
❑ VI a Y
N
d in N O U m U U
Page 4 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
AGENDA ITEM #3.A.
Page 5 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
MEMO
no umS
MEN
og�
Dpi
0
µ
C [U —
9 ?
C
a
Q
N
m
O
D}
j
-
u
-
0
o D c a
W
� ; m
m
O
G
O�°-
v°i
C
O
N
�
Z
..IE
f
n
O
2
=
o
0 0
D
U
�
a
a
o 0
m
C
O_
N
m
m
6
J
0
=
Y1
O O
m
°1
m
C
=
m
L
S
=
of
a o
�
C
�
O
O
m
o
0 0
a
¢
�
C
�
o
N
r
n
Y
Q
W
25
�
t
N
Q
N
W
�
m
J
O
O u
up
-C L2
a Z
o m
V
V1 x'03
F
est�v
o
r
<
Page 5 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
AGENDA ITEM #:.
»2872
Change Order No. aAmending Contract FY a,>,nArchitectural and Rmnee .
|
!
�
slit
-
}
•
!
;
j
�
aE;
^^
!
(/|§
�
(
»2872
Change Order No. aAmending Contract FY a,>,nArchitectural and Rmnee .
AGENDA ITEM O.A.
Page 7 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
I
_RSA
Engineering, Inc. Mechanical & Electrical Engineers
March 3, 2020
Jensen, Yorba, Wall
522 W. 10'h Street
Juneau, AK 99801
ATTENTION: Corey Wall
Dear Corey,
REFERENCE: Kodiak Island Borough Maintenance Building Boller Upgrades
Mechanical and Electrical Fee Proposal
RSA Engineering is pleased to offer a fee proposal for mechanical and electrical engineering
services for the referenced project. We have based our scope of work on your emails dated
2/28/2020 and the following assumptions:
General:
• As an alternate to the work proposed at the Borough Building, we will evaluate the feasibility
of replacing the boilers at the Maintenance Building and connecting the two together. We
will look at the option to replace the existing boilers in the Maintenance Building with a single
electric boiler sized for both buildings during lower demand portions of the year. Under this
option there will be new piping installed to connect the buildings and the bailers in both
buildings will be sized as a system.
• Electrical for the boiler project will include coordination with the utility for a new electric boiler
transformer and/or service, replacement of electrical distribution equipment and lighting in
the boiler room, and support for all new mechanical loads.
• We will perform a design site visit to review the systems at the Mechanical Building and
discuss the options with the KIB team to connect the buildings together.
• We will provide one design submittal, 35% Schematic Design. The submittal will include
drawings and design narrative.
Exclusions:
• We have not included time for any design services beyond 35% schematic design.
• We have not included cost estimation services.
RSA proposes the following lump sum fee for this project:
Prolect Deliverables Mechanical Electrical Expenses
Site Visit $2,160.00 $1,800.00 $1,053.00
35% Schematic Design $4,160.00 $3,340.00
GRAND TOTAL: $12,513.00
670 W. Flnweetl L. Sle 20 Mn ho,.,. M (907) ]]5-0521 1—ru-sk.mm
Page 7 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
AGENDA ITEM O.A.
Page 8 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
Man h 3.2020
Please review and advise if this proposal is acceptable by signing below and returning a copy to our
office as our notice to proceed. We have attached a copy of our Standard Terms and Conditions to
provide guidelines for contractual issues in the absence of a formal contract for this project. We look
forward to working with you on this project.
Sincerely,
Brian Pekar, P.E.
Associate Principal Engineer
bpp/jam/hhm
20-0110/P19-290
Attachment
Accepted for Jensen, Yorba, Wall
Page 8 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
AGENDA ITEM #3.A.
APPROVED BY ASSEMBLY ON 3/5/20
KODIAK ISLAND BOROUGH
TERM CONTRACT CHANGE ORDER
710 MILL BAY ROAD
Project Name: Project Number:
KODIAK, ALASKA 99615
Borough Building Boiler Replacement 469-614452.14020005.4
Contractor: Jensen Yorba Wall, Inc. Tenn Contract No.: 2019-10 Change Order No.: 07
Original Project Budget: $ 50,000.00 Original Contract: $ 0.00
Previous Budget Changes: $ 0.00 Previous Changes: S 260,756.00
Adjusted Project Budget: S 0.00 This Change: $ 39,767.00
To -Date Project Expenses: S 174.00 % of Original Contract >5%
To -Date Project Encumbrances: $ 0.00 Adjusted Contract: $ 300,523.00
Current Remaining Project Budget: $ 49,826.00
Description of Change Cost
Provide hazardous material survey, preliminary design documents and cost estimate for the Borough S 39,767.00
Building Boiler Replacement project per the proposal dated Febmary 21, 2020, to be charged an a time
and materials basis.
The time provided for completion of the contract is IS unchanged) (13increased) (Odecreased) by 0 calendar days. This document
shall become an amendment to the contract and all provisions of the contract will apply thereto.
Per Borough Code 3.30.100, a change order that does not exceed five percent of the original contract amount or $50,000,
whichever Is lower, requires approval by the mayor and deputy presiding officer, the mayor and one assembly member in the
absence of the deputy presiding office, or the deputy presiding officer and one assembly member in the absence of the mayor.
Change orders greater than rive percento a raved contract amount or $50.000, whichever is lower, require arsenuily approvat
Accepted By: Date:
Contractor's Representative
Recommended: Date: Date:
Engineering/Facilities Director Finance Director
Approved By: Date: Attest: Dale:
Borough Manager Borough Clerk
Mayor and Deputy Presiding Officer Approval (doer not escecdft'cperccm ofrhe anginal morract amount or 350,000, whichever is lower)
Approved By: Date: Date:
Borough Mayor Deputy Presiding Officer
Borough Assembly Approval (greater than fimpereent afapproved contract amount or $50,000, whichever Is lower)
Approved By: Date: Attest: Date:
Borough Manager - Borough Clerk
Revised 09119 Page 1 rf l
Page 9 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
AGENDA ITEM #3.A.
Page 10 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
■■■ Jensen
Yorba
Wall
WO
Imo' 522 West 10th Street, Juneau, Alaska 99601 907.506.1070 lensenyorbawall.com
Designing Community Since 1935
Date: February 22, 2020
To: Matt Gantlet
From: Corey Wall
Re: Kodiak Island Borough Building Mechanical Upgrade (JYW No. 19019)
Fee and Scope
Thank you for contacting us to assist in the design of the Kodiak Island Borough Building Mechanical Upgrade
project. Please find attached a breakdown of our fee proposal. The attached Individual fee proposals have
more detailed Information about the project scope, but the following is a summary of our understanding.
Projects fees are proposed to be a single phase. We are proposing the fees as Time and Expense and so have
not separated out the reimbursable travel expenses from the labor fees.
Scope of the project is as follows:
• Initial design work (through approximately 35% completion) of a limited mechanical upgrade at the
existing Borough Building. The Intent of this work will be to determine total project scope and costs to
assist the Borough in determining future projects.
• Project will Include replacement of the existing boiler system, water heater and generator.
• Project will Include hazardous material identification and abatement design for piping and Items as
required by the mechanical upgrade.
• Three options will be explored:
o Refurbishment and reinstallation of the removed boilers from PKIMC
o Two new oil -fired boilers
o Some combination of oil -fired and electric boilers
• Project will Include professional cost estimation of all options.
• Project will also Include an Indoor air quality investigation of the office areas of the entire building.
Please note the following assumptions:
• The proposal Includes a single site visit by EHS Alaska to conduct the hazardous material Investigation
and Indoor air-quality Investigation.
• Site visits by the architect or mechanical and electrical engineers have not been Included since the on-
site as -built Investigation was conducted previously. Photos, and any required as -built measurements
will be provided by KIB. Presentations and meetings about the project will be provided telephonically.
• The project does not Include architectural design work beyond as -built base drawings for the
engineers. It Is assumed this project will not Include layout changes or architectural upgrades.
Thanks again) We look forward to working with you.
Jensen Yorba Well Architecture Intenor Design Construction Management
Page 1 of I
Page 10 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
AGENDA ITEM O.A.
Page 11 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
J
N� .y n N N
n
■■
I"'
NNNNN NNN
�
■■■Q
Q
N N
01
N
C: m—
m.n�
m
C O
C r
a
a
�
a
p
-
a
5�
U
m C
a
p
O
O O j q y Q
Q
-
W
O O Q pp C y
m
U
J U N w 2 U W N 09
=
O
N
Z
2
2
Q
o p
txO
O
U
O
O
N
m
d
q
O
2
N
e0
W
n
c=
e
o 0
—
o
-
N
N
V
R
L
O
�
ry
ICE
E
m
o p
py
C
N
C
—
9
m
a
N
L
a
Q
d
N
LL
m
W
y
w
A
J WYE
mn
men mO
VI
'o
u m
�
LO
N
C Z
C E O
g
°
N �
ins
W
x
Page 11 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
AGENDA ITEM O.A.
Page 12 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
I
_RSA
Engineering, Inc. Mechanicel8 Electrical Engineers
February 21, 2020
Jensen, Yorba, Wall
522 W. 101h Street
Juneau, AK 99801
ATTENTION: Corey Wall
Dear Corey,
REFERENCE: Kodiak Island Borough Building Boller and Generator Upgrades
Mechanical and Electrical Fee Proposal
RSA Engineering is pleased to offer a fee proposal for mechanical and electrical engineering
services for the referenced project. We have based our scope of work on the following assumptions:
General:
• The project will consist of replacement of the existing boiler system, water heater, and
generator.
• We will provide one design submittal, 35% Schematic Design. The submittal will include
drawings and design narrative.
Mechanical:
• The boilers will be replaced with new boilers or with the salvaged boilers from the PKIMC
laundry project. For the new boiler option, we will include one electric and one oil fired boiler.
The boiler replacement will include replacement of all piping, pumps, boiler venting and
hydronic specialties in the boiler room. The existing ventilation equipment in the boiler room
will remain.
• The fuel oil day tank in the boiler room will be replaced. The new day tank will connect to
the existing fuel oil storage tank.
• The heal exchanger in fan room will be replaced with an electric hot water heater. Point of
use electric water heaters will be added at individual lavatories.
• Piping insulation from the boiler room through the crawlspace will be abated, we understand
the piping will be replaced as part of the abatement work.
Electrical:
• The generator in the boiler room will be replaced with a new exterior weatherproof packaged
generator unit with integral subbase fuel tank. The panelboards and automatic transfer
switch in the boiler room will be replaced.
• The design will include preliminary coordination with the electric utility for the electric boiler
option.
• The lighting in the boiler room will be replaced with LED lighting fixtures.
Exclusions:
• We have not included any site visits to Kodiak for the 35% submittal.
• We have not included time for any design services beyond 35% schematic design.
• We have not included cost estimation services.
670 W. Fl,..d Ln. 51e 200 BnUwr., l.R (901)176-0521 1 vmv.nvn4.wm
Page 12 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
AGENDA ITEM O.A.
Page 13 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
February 21. 2020
RSA proposes the following lump sum fee for this project:
Prolect Deliverables Mechanical Electrical
35% Schematic Design $4,560.00 $4,440.00
GRANDTOTAL: $9,000.00
Please review and advise if this proposal is acceptable by signing below and returning a copy to our
office as our notice to proceed. We have attached a copy of our Standard Terms and Conditions to
provide guidelines for contractual issues in the absence of a formal contract for this project. We look
forward to working with you on this project.
Sincerely,
Brian Pekar, P.E.
Associate Principal Engineer
bpp/jam/hhm
20-0089/1319-290
Attachment
Accepted for Jensen, Yorba, Wall
i
Page 13 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
AGENDA ITEM #3.A.
Page 14 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
EHS - Alaska, Inc. REVISED DATE: NA
FILENAME: P20.006 KIB KODIAK BOROUGH OFFICE BOILER & IAQ.XLSX ORIGINAL DATE: 01/22/20
PROJECT: KODIAK ISLAND BOROUGH, BOROUGH OFFICES BOILER REPLACEMENT & IAQ SURVEY
CONTACT: JENSEN YORBA WALL, INC. COREY WALL, AIA, PRINCIPAL ARCHITECT
AUTHOR: ROBERT FRENCH ASSIGNMENT: LIMITED ASBESTOS AND IAQ SURVEYS
SUMMARY OF FEES AND COSTS
TASK 1: INSPECTION AND SURVEY REPORT Page 2 $9,117
TASK 2: INDOOR AIR QUALITY SURVEY & REPORT Page 3 $8,796
TOTAL PROPOSED FEE; FIXED FEE, LUMP SUM: $17,913
SCOPE OF WORK & ASSUMPTIONS
I. This fee proposal is an estimate for professional services in accordance with EHS-Alaska's standard 2020 fee schedule, to support the
renovation of the Kodiak Island Borough Office Building, located in Kodiak, Alaska. Task 1 of the proposal includes a limited hazardous
materials survey related to replacement of the boilers, replacement of the heating piping in the building crawl space, and limited replacement
of heating equipment in the Fan Room. Task 2 of the proposal includes a limited Indoor Air Quality Study to determine the levels of fungi
(mold) and allergens present, and determine if nuisance miors arc present in occupied areas.
2. For Task I, EHS-Alaska will conduct a limited hazadaus materials survey for asbestos, lead and interior PCB materials, including sufficient
detail to serve as a basis of design for future renovations as described above. EHS-Alaska will prepare an abbreviated survey report, including
summarizing sample data with drawings of sample locations, but no design services. The survey will be limited to the Boiler Room, Crawl
Space, and the Fan Room. If the boiler replacement design extends beyond those limits, creation of future design documents my rely on
assumptions, or a possible future site visit, not included in this proposal.
3. Sampling will cause minor damage to finishes and surfaces sampled Samples will be collected from inconspicuous locations where possible.
However, repairs to damaged finishes are not included other than to prevent subsequent release of Potential asbestos fibers. No mof samples
am included in this proposal, and if future work includes creation of new morpenecradons, EHS-Alaska will either assume that there is debris
from the original asbestos BUR roof, or test during a possible furore site visit. Representative painted surfaces will be tested using a portable
X -Ray Fluorescence (XRF) lead analyzer. Other hazardous materials such as suspect mercury or PCB -containing materials will be noted, but
not sampled, including PCB's in paints or sealants. Materials suspected of containing PCBs or mercury will be assumed to contain PCBs or
mercury unless it is labeled "PCB Free" or "No PCBs" or previous testing has determined it to be PCB or mercury free. Free and complete
access to all spaces will be provided by the Owner, and copies of available as -built information and floor plans will be provided to EHS by the
Owner. This proposal assumes that reasonably accurate AutoCAD backgrounds of the existing Boor plans will be provided to EHS-Alaska
for use in the teport.
4. For Task 2,EHS-Alaska will perform a limited IAQ investigation of the Borough Once Building, focusing an the office areas. EHS-Alaska
will conduct a limited mold investigation to identify signs and symptoms of conditions which may have caused or have the potential to cause,
fungal growth, including use of an inflated concern and moisture motor testing of areas with visible water damage or evidence of previous
leaks. EHS-Alaska will conduct sirbome "Total" mold spore sampling in 5 areae in the building in complaint areas, including areas with
suspect fungal growth (if present), along with one outdoor, and one indoor "control" sample in a nun -complaint arca. Destructive testing will
not be conducted. All samples along with a chain ofcustody will be submitted to an Environmental Microbiology (EMLAP) Accredited
Laboratory that participates in the American Industrial Hygiene Association (AIHA) Laboratory Quality Assurance Progrem (LQAP). The
limited mold assessment will be conducted by an industrial hygienist experienced in mold assessments and investigations based on ASTM
E2418 (Standard Guide for Readily Observable Mold and Conditions Conducive to Mold in Commercial Buildings: Baseline Survey Process).
ASTM D7338-14 (Standard Guide for Assessment of Fungal Growth in Buildings) and ANSIAICRC 5520 Standard and Reference Guide for
Professional Muld Remediation EHS-Alaska will take 5 carpet dust samples for analysis for allergens.
5. Two of the EVM-7 Environmental/IAQ monitors will be operated in survey mode during the initial visual inspection, and be programmed for
PM2.5 and PMIO dust analysis. EHS-Almka will switch all 3 EVM-Ts to PMIO mode, and conduct 2 days of IAQ data logging in amen to be
determined onsite sated by the mein Air Handling Unit. A third EVM-7 will be placed in the Assembly Chamber's wing.
6. The EVM-7 instruments measure 7 environmental parameters: Volatile Organic Compounds, Airborne Particulates, Carbon Monoxide,
Carbon Dioxide, Temperature, Relative Humidity and Dew Point. EHS-Alaska will review all daw4ol ged levels and compare and contrast
those levels with OSHA, ACGIH and NIOSH standards or guidelines.
7. EHS-Alaska will deploy 4 redo. moniters in the lower level and Assembly wing. The monitors require at least 48 hours ofexpasum.
8. EHS-Alaska proposes to provide the above described monitoring and summary report on a fixed fee basis. This proposal excludes any and all
industrial hygiene activities nut specifically mentioned above.
To authorize the work described above under the terms contained In this proposal, please sign this page and return as a Notice to
Proceed.
Signature Date
PROPOSAL IS VALID FOR 90 DAYS FROM DATE OF SUBMITTAL
PAGE i OF 3
Page 14 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
AGENDA ITEM #3.A.
Page 15 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
EII$ - Alaska, Inc. REVISED DATE: NA
FILENAME: P20-006 KIB KODIAK BOROUGH OFFICE BOILER & IAQ.XLSX ORIGINAL DATE: 01/22/20
PROJECT: KODIAK ISLAND BOROUGH, BOROUGH OFFICES BOILER REPLACEMENT &IAQ SURVEY
CONTACT: JENSEN YORBA WALL, INC. COREY WALL, AIA, PRINCIPAL ARCHITECT
AUTHOR: ROBERT FRENCH ASSIGNMENT: LIMITED ASBESTOS AND IAQ SURVEYS
TASK 1: INSPECTION AND SURVEY REPORT
CODE\TASK PRIN CM IH/SPM PM -1 PM -2 CAD ADMIN
60 PROJECT TRAVEL 0.0 0.0 9.0 0.0 0.0 0.0 0.0
44 TRIP PREP, REVIEW EXISTING DATA 1.0 0.0 4.0 0.0 0.0 0.0 0.0
50 FACILITY SURVEY 0.0 0.0 14.0 0.0 0.0 0.0 0.0
48 SURVEY REPORT 1.5 0.0 6.0 0.0 0.0 2.0 0.0
44 PROJECT MGMT. 1.0 1.0 2.0 0.0 0.0 0.0 0.5
Hour Totals: 3.5 1.0 37.0 0.0 0.0 2.0 0.5
Billing Rate: $168.00 594.00 1155.00 $135.00 $135.00 $135.00 568.00
Wage Subtotals: $588 $94 $5,735 SO SO $270 $34
LABOR COSTS:
DIRECT LABOR SUBTOTAL: $6,721
DIRECT COSTS:
PHOTOGRAPHY: 515
REPROGRAPHICS: $20
COURIER (NONE, ELECTRONIC): SD
EQUIPMENT (XRF LEAD ANALYZER DAYS): 3.0 Q $I50/DAY $450
EQUIPMENT(HI•FLO AIR PUMP, DAYS): 0,0 Q 120/DAY $0
SURVEY CONSUMABLES: 850
PHONE/FAX: $5
SAMPLE SHIPPING: 1 Q $35 EACH $35
DIRECT COST SUBTOTAL: 8575
DIRECT COST MARK UP Q 10.00% = 158
LABORATORY COSTS:
ASB. BULK PLM EPA 600/R93/I 16, 3 DAY 50 Q $8.00/LAYER $400
ASB. BULK ROOF PLM EPA 600,3 DAY 0 Q $12.00/LAYER $0
ASB. MICROVAC DUST ASTM D5756,5 DAY 0 8 5150/SAMPLE $0
Pb PAINT/SOIUDUST SW 846-70008:7420, 5 DAY 0 Q 55.45/SAMPLE $0
Pb TCLP SW 846-1311, 5 DAY 0 Q $56/SAMPLE $0
PCB BULK CAULK/CONC/PAINT SW846,1 WK D QSI74/SAMPLE $D
PCB AIR NIOSH 5503, MODIFIED, I WEEK 0 Q $361/SAMPLE $0
PCB WIPE/SOIL EPA SW-8463550C/8062A,I WK 0 @S156/SAMPLE SO
"••"•
LABORATORY COST SUBTOTAL: 5400
LABORATORY COST MARK [JP ® 20,00% _ $80
TRANSPORTATION COSTS:
AIRFARE &EXCESS BAGGAGE: $600
TAXI: 10
AIRPORT PARKING (3 DAYS Q $16/DAY): 548
RENTAL CAR (3 DAYS ®$60/DAY): $180
LODGING (2 NIGHTS X 1 PERSON Q SI25MIGHT): 5250
MEALS (3 DAYS Q S60/DAY): $180
MILEAGE ®_ $0.575 45 miles $26
TRANSPORTATION COST SUBTOTAL: $1,284
TOTAL COSTS, THIS SHEET: 59,117
'•••• PROPOSAL IS VALID FOR 90 DAYS FROM DATE OF SUBMITTAL
PAGE 2 OF 3
Page 15 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
"••"•
Page 15 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
AGENDA ITEM #3.A.
Page 16 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
EHS - Alaska, Inc. REVISED DATE: NA
FILENAME: P20-006 KIB KODIAK BOROUGH OFFICE BOILER & IAQ.XLSX ORIGINAL DATE: 01/22/20
PROJECT: KODIAK ISLAND BOROUGH, BOROUGH OFFICES BOILER REPLACEMENT &IAQ SURVEY
CONTACT: JENSEN YORBA WALL, INC. COREY WALL, AIA, PRINCIPAL ARCHITECT
AUTHOR: ROBERT FRENCH ASSIGNMENT: LIMITED ASBESTOS AND IAQ SURVEYS
TASK 2: INDOOR AIR QUALITY SURVEY & REPORT
CODE\TASK PRIN CM Ili/SPM PM -1 PM -2 CAD ADMIN
44 REVIEW AS -BUILT DATA, SURVEY PREP 1.0 0.0 2.0 0.0 0.0 0.0 0.0
50 LTD. VISUAL [NSP. &DUST MONITORIN( 0.0 0.0 3.0 0.0 0.0 0.0 0.0
50 FUNGAL INSP. &AIR SAMPLING 0.0 0.0 4.0 0.0 0.0 0.0 0.0
50 EVM-75ET UP 0.0 0.0 1.0 0.0 0.0 0.0 0.0
50 EVM-7 PICK-UP & DOWNLOAD 0,0 0.0 2.0 0.0 0.0 0.0 0.0
44 RADON TESTING 0.0 0.0 1.5 0.0 0.0 0.0 0.0
48 DATA ANALYSIS 1.0 0.0 8.0 0.0 0.0 0.0 0.0
48 INTERPRETIVE REPORT 2.$ 0.0 14.0 0.0 0.0 0.0 0.0
44 PROTECT MGMT. 1.0 1.0 0.0 1.0 0.0 0.0 1.0
How Totals: 5.5 1.0 35.5 1.0 0.0 0.0 1.0
Billing Rote: SI68.00 $94.00 $155.00 $135.00 $135.00 $135.00 $68.00
Wage SuhtaWls: $924 894 $5,503 $135 $0 $0 $68
LABOR COSTS:
DIRECT LABOR SUBTOTAL: $6,724
DIRECT COSTS:
PHOTOGRAPHY: $IS
REPROGRAPHICS: $20
COURIER (NONE, ELECTRONIC):- $O
EQUIPMENT (EVM-7, IAQ MONITOR WEEK): 3.0 Qa S336/WEEK $1,008
MOISTURE METER (1 METER 3 DAYS) 3 Q $10/Day $30
BORESCOPE 0 @$16/Doy SO
IR CAMERA (1 CAMERA, 3 DAYS) 3 8 $26/Day $7$
MOLD AIR SAMPLING CASSETTES 7 Q S7/Each $49
MOLD WALL CAVITY KITS 0 Q$II/Each SO
SURFACE SAMPLE KITS 0 @$I/Each $0
.
HIGH VOLUME PUMP I Q $20/Each $20
BIOS PRIMARY CALIBRATOR 1 Q 536/Each $36
SURVEY CONSUMABLES: $26
SAMPLE SHIPPING: I Q $3$ Each $36
•""•"
DIRECT COST SUBTOTAL: $1,312
DIRECT COST MARKUP @ 10.00% _ $131
LABORATORY COSTS:
ASB. BULK PLM EPA 600/R93/116, 3 DAY 0 @ 57.00/LAYER $0
MOLD AIR SAMPLE 7 Q S36/Sample $175
DUST ALLERGEN ANALYSIS 5 QS36/Samplc SIMRADON
TEST KITS & ANALYSIS 5 Q530/Kit $150
LABORATORY COST SUBTOTAL: $606
LABORATORY COST MARK UP Q 20.00%a = $101
MILEAGE ®_ $0.$75 40 miles $23
TOTAL COSTS, THIS SHEET: 58,796
•"•" PROPOSAL IS VALID FOR 90 DAYS FROM DATE OF SUBMITTAL
PAGE 3 OF 3
Page 16 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
•""•"
Page 16 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
AGENDA ITEM #3.A.
Page 17 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
Fee Proposal
H M S
4103 Minnesota Drive • Anchorage, Alaska 99503
p: 907.561.1653 k 907.562.0420 maii@hmsalaska.com DATE PROPOSAL NO.
2/21120 P20-02-14
To:
Jensen Yorba Wall, Inc.
522 West 10th Street
Juneau, Alaska 99901
Attn: Corey Wall
Project: Borough Building Boiler Replacement
Location: Kodiak Island, Alaska
1. Project Description and Service
Provide cost estimate for three boiler replacement options including hazmal abatement, generator replacement,
heat exchange demolition, addition of point of use water heaters, and replacement of crawlspace
distribution piping.
Estimate will be prepared in Uniformat Elemental Categories and priced for construction on a dale to be
determined.
2. Fee Breakdown and Schedule (Lump Sum)
35% Design Estimate $ 5,248 Within (9) Full Working Days
The above fee does not include preparation of additive bid items or alternates. See 3. Terms below.
Allow the above full working days to provide the proposed services. Time for task completion will begin following
receipt of all available design information for that particular phase. Please note the above durations exclude
weekends, holidays and partial days. Please give two weeks advance notice for commencing each phase of work.
3. Terms
Deliverable:
HMS Inc, will provide a copy of our estimate via email In a PDF file format or in Excel, If necessary. Should
a hard copy of the estimate be necessary, at your request, a bound or loose copy will be provided to you.
Drawings:
Architect/Engineer shall provide HMS Inc. with full size, correct scale drawings, along with an electronic
set (PDF format preferred). Should these not be provided, It may be necessary to Increase our fee proposal
and add additional days to complete our work.
Should it be necessary, HMS Inc. has the capability to print one or two drawings, however, depending on
the quantity, an additional charge may be added at $4.00/sheet.
Page 1 of 3
Page 17 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
AGENDA ITEM W.A.
Page 18 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
Fee Proposal
H M �
3. Terms (Continued)
Additive Bid Items or Alternates:
Our fee proposal does not include preparing estimates for additive bid items or alternates (except those
Included in Section 2 Fee Breakdown) that require re -measurement of work Items Included in the Base Bid
cost estimate. We reserve the right to renegotiate our fee should alternates become necessary beyond
one or two minor alternates or additive bid items.
Reimbursable Expenses:
This fee proposal does not provide for long distance phone calls, site visits, meetings with the owner, or
any other unforeseen expenses unless listed in Section 2. Fee Breakdown. Any such items, if required,
will be charged on a time -and -expense basis at our current rate schedule.
Penalty/Bonus Condition:
This proposal is made on the understanding that we will not be entering into an agreement with the client
that Includes a penalty/bonus condition dependent on the outcome of the bid. Should such a clause be
required, we reserve the right to modify our proposal or possibly withdraw from the project.
Additional Insured:
Any requirements to name additional Insureds on our Insurance policies may be subject to additional fees
should fees be added to our policy by our carrier.
Payment Terms:
Payment shall be made within (45) days of Invoice date. Delayed payment beyond that period Is subject
to a 1.5% fee per month.
Expiration Date:
This fee proposal is valid for (6) months from the date of issue. HMS Inc. reserves the right to adjust the
fee to incorporate the current years rales after the (6) month period.
Change in Scope:
Should the project scope or format change, HMS Inc. reserves the right to modify this proposal. Written
approval for work on increased scope items prior to proceeding with additional work will be required.
Notice to Proceed:
Designeriowner will provide written notice to proceed. Delivery of documents is not considered a notice
to proceed.
Prepared By
I�
Kent Gamble, Principal
KGlkig
Page 2 of 3
Page 18 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
AGENDA ITEM #3.A.
Page 19 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
H � �
4103 Minnesota Drive • Anchorage, Alaska 99503
p: 907.561.1653 l.. 907.562.0420
mail@hmsalaska.com PROPOSAL NO.
P20-02-14
FEE BREAKDOWN
(2020 SCHEDULE OF RATES)
Project: Borough Building Boiler Replacement A/E Firm: Jensen Yorba Wall, Inc.
Location: Kodiak Island, Alaska
Date: 2/21/20
Prepared By: Kent Gamble, Principal
Total
Total
Discipline Rate
Hours Subtotal Hours
Fee
35% Design Estimate:
Estimator V 165.00
x 1 = 165.00
Estimator IV 144.00
x 16 = 2,304.00
Estimator 111 134.00
x 10 = 1,340.00
Estimator 11 115.00
x 10 = 1,150.00
Estimator 1 77.00
x 0 = 0.00
Office Support II 77.00
x 3 = 231.00
Office Support 1 58.00
x 1 = 58.00
Total 35% Design Estimate:
41 Hours
$ 5,248.00
TOTAL:
41 Hours
$ 5,248.00
Page 3 of 3
Page 19 of 19
Change Order No. 8 Amending Contract FY2019-10 Architectural and Enginee...
Kodiak Island Borough
Assembly Special Meeting Guidelines
March 12, 2020, Immediately Following The Work Session
School District Conference Room
1. ROLL CALL
KIBC 2.25.070.... the Chair shall cause the record to reflect the absence of the member, the
REASON for the absence, and whether the absence is excused by the Assembly.
Recommended motion: Move to excuse Assembly Member who is absent due
to personal leave.
VOICE VOTE ON MOTION.
2. CITIZENS' COMMENTS (These are limited to three minutes per speaker.)
ASK SPEAKERS TO SIGN IN AND STATE THEIR NAME FOR THE RECORD.
3. CONSIDERATION OF MATTERS IN THE CALL FOR THE SPECIAL MEETING
A. Change Order No. 8 Amending Contract FY2019-10 Architectural and Engineering
Services Term Contract for Design for the Borough Building Boiler Room
Renovation
Recommended motion: Move to authorize the Borough Manager to execute change
order No.8 amending Contract FY2019-10 with Jensen Yorba Wall, INC. for
Architectural and Engineering services term contract in an amount not to exceed
$22,004.
Staff Report — Manager Powers.
Assembly discussion.
ROLL CALL VOTE ON MOTION.
B. EXECUTIVE SESSION - Borough Clerk's Performance Evaluation
Recommended motion: Move to convene into executive session to discuss the
Borough Clerk's Performance Evaluation, a subject that qualifies for executive
session as a matter that may tend to prejudice her character or reputation.
ROLL CALL VOTE ON MOTION.
Recommended motion: Move to invite the Mayor and Assembly into executive
session.
VOICE VOTE ON MOTION
After the vote, Mayor Roberts recesses the special meeting and convenes the executive
session.
Upon returning from the executive session, Mayor Roberts reconvenes the special
meeting and announces:
Kodiak Island Borough Assembly Guidelines
March 12, 2020 Page 1
• The Assembly discussed the Borough Clerk's Performance Evaluation and
• No action is to be taken as a result of the executive session
• The Assembly may make a motion if necessary. The Assembly must state the motion
and vote outside of executive session.
ROLL CALL VOTE ON ANY MOTION.
4. ADJOURNMENT
Recommended motion: Move to adjourn the meeting.
VOICE VOTE ON MOTION.
Kodiak Island Borough Assembly Guidelines
March 12, 2020 Page 2
Z-zl
§
\
a
S
0
�
k
\
«
§
0
0
z
«
§
�
a
§
�
�
TA
2
2
%
\
\{
\
>
k
§
/
\�
z
)
.
�
2
0)
\
)
)
/
(
b
$
o
k
¥
5
±
±
±
6
(
/
]
LU
U,
�
�
%
/
_
°
\2
k
.
0
(
/
a
°±
\
\
\
§
/
S
f
(
/
{
k
¥
£
5
£
■
6
£
\
/
)]
@
ko(
§�
0
)
@
C'.
jp
Co
k.§/
F-
\
j
B
\
o>
G
#
Q
2
/
„ S
#
6«
E\
m @
§
/
£
k
§
k
/
(
2
z
/]
\
«
E
/
)
Q
r
L
{
k
\
\
(
§
\
{
\
>
R
a
I
o/
f
R«
9
9\
o&
s
mLU
±
6
6
I££
z(
\§
2
7 #
§co
0
%
,
E
/
k
�
13
z
b
,
/
/)
/}
)\
_
«\\
m U
§
§
N
ca
❑
too
ICA
a
U)
N
N
CDU
N
A
.4
v.
d
7
O'
N
C
G1
N
N
CL
V
C
N
� c
�o
m
d
C �
N O'
N N
N �
a�
Ln 'y
v a 00i
c
mu
5.6m
C C N
N X �
m O
ao
co — O
� N
m '
vm E
o `o
c Q
N
(D N C
U. aa) L
N
m
N L
U N N
0'a E
�ECD=
O> N O
M O T
N L -
O
o CO N
-Oc E
o 0
�•M .O
N O
N N w
O o Q
O N N
2 w 2
z
N
>
a
}
E
CD
N
L
CNO
U
O
N
CD
O
O
O
>
U
T
c
W
O
dai
¢
n
�U
o
W
O
n
ca
,m
o
w
d
Z
L
W
m
>
Z
L
¢
m
L
m
N
=
�i
N
Nin
y
C
O
N
c
m
c
O
E
m
r
N
«
U7
S]
o
❑
C
U
m
o
C
w
Cof
O
¢
❑
Y
co
(n
H
J¢
m
O
} W
m N
y
N
W
ZO
0
F
(D
m
Cc)
n
2 o
¢
m
❑
J
_T
E
U)
LU
}
>
O
N
m
L
01
N
N
N
O
w•
w
N
L•
)
N
❑
m
C
o
O
c
E
N
~
U
Z
O
>
((
E
O=H
U
¢
W
>
} W
O
m
o
w
C7Z
NsNTo3NCd
c0
LU
UOYO
mO
co
N
v
ai.
Om
E
E>z
w
J
U
¢
j
U)
Z
Oa0
m W
QI
O
❑J
OZ
O
oC
W
T
E
U`
N
c
O
m
E
N
m
y
`O
cm
2a�
c
E
C
L
0
af
L
Y
V7
H
J
H
U
Q
D
Y
(n
<
m LU
OF
v.
d
7
O'
N
C
G1
N
N
CL
V
C
N
� c
�o
m
d
C �
N O'
N N
N �
a�
Ln 'y
v a 00i
c
mu
5.6m
C C N
N X �
m O
ao
co — O
� N
m '
vm E
o `o
c Q
N
(D N C
U. aa) L
N
m
N L
U N N
0'a E
�ECD=
O> N O
M O T
N L -
O
o CO N
-Oc E
o 0
�•M .O
N O
N N w
O o Q
O N N
2 w 2
SPr�i 4 L- K SESSION
vla,1�114 t � ? � -d
SCOTT ARNDT ATTENDED_ ABSENT
DUANE DVORAK ATTENDED ABSENT
JULIE KAVANAUGH ATTENDED ABSENT
ANDY SCHROEDER ATTENDED ABSENT
REBECCA SKINNER ATTENDED ABSENT
DENNIS SYMMONS ATTENDED_ ABSENT
JAMES TURNER ABSENT
MAYOR ROBERTS ATTENDED ABSENT