FY2018-43 MOA Between KIB and Kodiak Soil & Water Conservation District Regarding Lake Orbin Culvert Replacement ProjectKodiak Island Borough
Manager's Office
710 Mill Bay Road
Kodiak, Alaska 99615
Phone (907) 486-9301 Fax (907) 486-9374
MEMORANDUM OF AGREEMENT BETWEEN
THE KODIAK SOIL & WATER CONSERVATION DISTRICT AND THE KODIAK ISLAND
BOROUGH
REGARDING THE LAKE ORBIN CULVERT REPLACEMENT PROJECT ASSOCIATED
WITH A COOPERATIVE AGREEMENT TO THE KODIAK SOIL & WATER
CONSERVATION DISTRICT FROM THE U.S. FISH AND WILDLIFE SERVICE
PURPOSE:
This Memorandum of Agreement (Agreement) recognizes that the Kodiak Sail & Water
Conservation District is the real and appropriate entity relative to the Culvert Replacement
Project funded under Cooperative Agreement F13AC00878 and F16ACOI034 issued by the U.S.
Fish and Wildlife Service. These Agreements outline the terms under which the Kodiak Sail &
Water Conservation District and the Kodiak island Borough agree to substitute the Kodiak lsland
Borough as the Contractual Authority fbr Construction for the Cooperative Agreements
F13AC00878 and F16AC01034, attached hereto as Exhibits A, B, C and D, and hereby
incorporated by reference and consistent with the following:
PROJECT TITLE: THE LAKE ORB1N CULVERT REPLACEMENT PROJECT
AGREEMENT EFFECTIVE DATE: June 1, 2018
AGREEMENT COMPLETION DATE: August 31, 2021
COOPERATIVE `AGREEMENT TERM: As per Agreements F13AC00878 and FI6AC01034,
the U.S. Fish and Wildlife Service shall reimburse the Kodiak Soil & Water Conservation
District for the �erifotlnance of the project work under the terms outlined in the agreements. The
amount of the payment is based upon project expenses incurred, which are authorized under this
agreement. See attached Cooperative Agreements.
THE KODIAK SOIL '& WATER CONSERVATION DISTRICT SHALL:
I . Forward the requested funds to the Kodiak Island Borough to pay the Selected Contractor
as awarded by the Kodiak Island Borough through the completed bidding process for the
project construction and administrative costs. Upon written request from the Kodiak
Island Borough, Kodiak Soil & Water Conservation District will forward funding in an
amount to pay invoice costs.
2. Release the Kodiak Island Borough from any future requirement to comply with all grant
provisions.
U.S. FISH AND WILDLIFE SERVICE SHALL:
1. Provide funding, assistance, project development for dcsit and scope, administrative
review and guidance for on-site installation of the facilities.
2. Provide funding to the Kodiak Soil & Water Conservation District upon written request.
KODIAK ISLAND BOROUGH SHALL:
1. Assist in the project development and completion to include the solicitation for bids,
manage the bidding and contract award process, and administer the contract for
construction of the project.
2. Provide to the Kodiak Soil & Water Conservation District all documents associated with
the grant administration relative to Grants F13AC00878 and FI6AC01034.
DATED:
ichael Pow s, Manager Blythe Town, District Manager
Kodiak Island Borough Kodiak Soil & Water Conservation District
518 W. Marine Way, Suite 206
Kodiak AK 99615
ATTEST: Phone (907) 486-5574
......--
U�SX,P►ND Bp�O
Nova M. Javier, MMC Q G
Kodiak Island Borough C
q�ASKA�`1�
C x Nr 6 7T rq
a:a
ants � m>vn
United States Department of the Interior a""a
U.S. FISH AND WILDLIFE SERVICE
1011 East Tudor Road
Anchorage, Alaska 99503.6199
R4 REPLY REFER TO:
AFWFO
Blythe Brown
Project Coordinator
Kodiak Sail and Water Conservation District (KSWCD)
51 S Marine Way, Suite 206
Kodiak, Alaska 99615
DUN: 130455475
Subject: Notice of Revision 02 to Financial Assistance Award F13AC00978
Dear Ms. Brown,
Your organization's request for award revision to U.S. Fish and Wildlife Service (USFWS) Award
FI3AC00878 titled "Lake Drain Fish Passage Project" under CFDA 9 15.608 is approved cfrective
8'12015. This oward is revised as follows:
USRVS is revising the award to provide a supplemental revision to change the end date of this
agreement fmm December 31, 3015 to December 31, 2016 at no additional cost to the U.S. government.
The revision also includes two additional culverts in lite Lake Orbin drainage for possible survey and
design. The original scope ofwork and 2014 revision provided for the survey, design and construction
ofthree fish friendly culverts on the stream from Lake Orbin to improve spawning and rearing habitat
For collo, chum and sockeye salmon. This revision allows KSWCD to conduct surveys and secure
designs For one or two more culverts in the Lake Orbin drainage depending on time and design cost.
The two potential culverts are located an Lake Orbin Drive (ADFGH 20700845) and Middle Bay Drive
(ADF(34 30700852). Continuing to replace these priority road crossings for fish passoge strengthens the
original proposal and enhances salmon populations for the benefit oFlhe resources and the American
people.
This revision also changes ilia USFWS Project Officer from Bill Rice to Franklin Dekker; please see the
Project Contract section for full details.
The award Terms and Conditions have changed to reflect the new 2 CFR 200 Regulations, see the
Terms and Conditions section.
FM F13AGC37E Revrilm 7 olr?aots Pape 1 cta
The original performance and budget period of this award has been changed to extend the end date from
December 31, 2015 to read a new end date of December 31, 2016.
The revised performance and budget period of this award is November 1, 2012 through December
31, 2016. This is the period of Federal sponsorship. Only allowable costs resulting from obligations
incurred during this funding period and may be charged to this award.
Project Performance Measurement:
The Recipient will be monitored far required Reporting; i.e. Performance Reporting, Financial
Reporting and all other Mandatory Reporting as identified in the Notice of Award Letter.
The following scheduled tasks have been revised. All o0rer project tasks; activities, objectives, and
dcliverabics, set forth in the original award and any previous revisions (modifications/amendments) ere
also applicable to, and are hereby incorporated by reference into this revision.
Performance Goatsfrashs: project activities, objectives, and deliverables
Anticipated
Survey, locales. eolechnlcal investi ations
Completion Data
Completed
Desi ns, bid documents completed
Cam Ieted
Con. r
Com leted
533,261.00e
culvert
cult'
First culvert constructed
colt
Cam Ieted
Phase Z
Original Award:
Designs, bid documents completed
November 30,
Contractor selected
2014
March 30.2015
Second
Second culvert constructed
December 30,
One or two additional culvert survey and/or dcsign(s) for fish passage
2015
December 31,
2016
The Recipient's project officer must immediately communicate (via Ielephone, fox or email) any
significant changes to (a) project objectives, (b) the above schedule, (e) approved budget, or (d) project
personnel, and then document these changes (along with an explanation or why they occurred and
suggestions on how to deal with them) in a Significant Development Report (SDR). Please sec the
Significant Development section ofthls award letter for details.
This award is funded as follows:
Description ofActiva
USFWS
Re (lent
Revision 2:
No cost time extension and minor scope of work change
50.00
50.00
Revision
5100,000.00
533,261.00e
Increase in fundin for Phase2
Original Award:
595,000.00
S10,000.00
An•ard Total:
5195,000,00
543,261.00
WAS FI3ACnaara Fitm;r, 2 D&7Mo15 Page 2ora
System �orAward Inasement fSAD1) RcaNtroUon:
Under the terms and conditions ofthis award, your organization must maintain on active SAM
registration at hhns:/Avtvwsam P+ay/nnrtoyouhlirJSAM%until the Final financial report is submitted or
final payment is received, whichever is later. If your orgnnizalion's SAM registration expires during the
required period, the Service will suspend payment under this and all other Service awards to your
organization until you update your organization's SAM registration.
Terms orAecentanca:
NOTE: The terms and conditions of this award have changed to incorporate the new 2 CFR 200
Regulation, please revinv these at the website listed.
Acceptance ofa Financial assistance award (i.e., grant or coopcmlive agreement) from the Service
carries with it the responsibility to be aware of and comply with the terns and conditions applicable to
the award. Acceptance is defined as the start of work, drawing down funds, or accepting the award via
electronic means. Awards arc based on the application submitted to and approved by the Service.
Awards are subject to the terms and conditions incorporated into the notice oraward either by direct
citation or by reference to the following: Federal regulations; program legislation or regulation; and
special award terms and conditions. The Federal regulations applicable to Service awards arc listed by
recipient type in the Service Financial Assistance Award Terms and Conditions posted on the
lntemet nt httn://unvw•fws uov/mmnts/. If you do not have access to the internet and require a full text
copy of the award terms and conditions, contact the Service Project Offccr.
Snegial Conditions aad Pravisioas:
All special conditions and provisions applicable to the original award and any previous revisions
(mndifrcationslamendments) are also applicable to, and ore hereby incorporated by reference into, this
revision.
Payments
Your organization has completed enrollment in U.S. Treasury's Automated Standard Application for
Payment (ASAP) system. Please continue to use your USFWS award number, for all payment actions.
The ASAP Help menu provides general information on payments. Select the Payment Requestor
Tutorials Help menu option to walk through how to request funds.
NOTE: iry'ou are having problems oerrd efileulties wilt ASAP, please go to the USFWS \Viki page at:
if you were not able to find what you need from the above information, please contact the Branch of
Financial Assistance Systems (FAS) directly at; fvvliafas(alfws eov and include the following
information: (Recipient Nome, Person rq Contact, Phonc Numhcr, ASAP Recipient ID, FHhIS Award Numbers (irumum
ask their Service Project orRcer for this Information). Description urEmort tesvae). Please be very specific. Provide
a screen shot if possible.
Reportine Requirements:
Financial and Performance Re 2rdna Reguiremen •
The Financial and Performance Reporting requirements have been revised based on the extension set
Forth in this revision. All other reporing requirements as detailed in the original notice ofaward and
FWS F13AC00878 Rr'nccn 2 UrerVIS Page 3oie
any previous revisions (modifrcationslamendmcnis) are also applicable to and are hereby incorporated
by rcrerence into this revision. See the fallowing revised reporting schedule:
Report: Report Period: I Rc orl Due Dale:
Reports required prior to this rerlsiah (USFtfS should lave on file)
Interim financial &
erformance re rts
Novmber 1, 2012 - November I,
2.13e
March 31, 2014
Interim financial &
rformance reports
November 2, 2013 - November 1,
2014
March 31, 2015
REMAINING REPORTS DUE:
Interim financial &
porromoncc reports
November 2, 201 -December 31, 2015
March 31, 2016
Final Perfomance Report
lanuary 1, 2016 - December 31, 2016
March 31, 2017
Final Ffnanclnl Repan
November I, 2012 - December 31, 2DIG
March -31,2017
Recipients must use the Standard Form (SF) 425, Federal Financial Report Ibm for all financial
reporting. This form is available at litipd/wtvtv.whitehouse.govlamNgrnnts_fomsl.
Performance reports must contain: 1) a comparison oractual accomplishments with the goals and
objectives of the award as detailed in the approved scope or work; 2) a description or masons why
established goals were not met, If appropriate; and 3) any other pertinent information relevant to the
project results. Please include the Service award number provided In the subject line ofthis Iencron all
reports.
Financial and perromance reporting due dates may be extended by the Service upon receipt of a written
request addressed to the Service Project Officer identifying the type ormport to be extended, the
requested revised due date, and a justification for the extension. The Service Project OMccr may
Approve an additional extension irjustified by a catastrophe that significantly impairs the recipient's
operations. Requests ror reporting due date extensions must be received by the Service Project Officer
no later than one day before The original reporting due date.
Significant Developments Repnrts:
Events may occur between the scheduled performance reporting dates that hate significant impact upan
the supported activity. In such cases, notify the Service Project Officer in writing as soon as the
following types of conditions become known:
• Problems, delays, or adverse conditions that will materialiv impair the ability to meet the
objective of the Federal award. This disclosure must include a statement orally corrective
action(s) taken or contemplated, and any assistance needed to resolt a the situation.
• Favorable developments that enable meeting time schedules and objectives sooncrorat less cost
than anticipated or producing more or different beneficial results than originally planned.
FWS F13•C00678 aeN0-x2 aar2WDi� PXte 4ala
DLiter Deliverables:
Delivera6lc Submission lnstructions/Detnils Deliverable Due Date
One ar ti% culvert survey I Email pdr March 31, 2017
Land or design(s)
All reports, survey and or design results must be sent to the Service Proiect Officer.
/Yonflict orinterest Disclosures:
Recipients are responsible for notifying the Service Project Officer in writing of any actual or potential
conflicts of interest that may arise during the life of this award. Conflicts of interest include any
relationship or matter which might place the Rcciplcnt, the Recipient's employees, orthe Recipient's
subrecipients in a position of conflict, real or apparent, between their responsibilities under this award
and any other outside interests. Conflicts of interest may also include, but are not limited to, director
indirect financial interests, close personal relationships, positions or trust in outside organizations,
consideration of future employment arrangements with a different organization, or decision-making
affecting the award that would cause a reasonable person with knowledge arthe relevant facts to
question the Impartiality arthe Recipient, the Recipient's employees, or the Recipient's subrecipients in
the matter. Upon receipt of such a notice, the Service Projcct Officer in consultation with their Ethics
Counselor will determine If o conflict of interest exists and, if so, iFthere are any possible actions to be
Laken by the Recipient, the Recipient's employee(s), or the Recipient's subrecipient(s) that could reduce
or resolve the conflict. Failure to resolve conflicts of interest in a manner that satisfies the Service may
result in any oFthe remedies described in 2 CFR 200.338, Remedies for Noncompliance, including
termination or this award.
Other Mnndutory Diselosures:
Recipients and their subrecipients must disclose, in a timely manner, in writing to the Service or pass-
through entity all violations orFederal criminal law involving fraud, bribery, or gratuity violations
Potentially affecting this award. Failure to make required disclosures can result in any of the «medics
described in 2 CFR 200.338, Remedies for noncompliance, including suspension or debarment (See ?
CFR 200.113, 2 CFR Pan 180, and 31 U.S.C, 3321).
Prolect Plan and Dud et Amendments:
Recipients are permitted to re -budget within the approved direct cost budget to meet unanticipated
requirements and may make limited program changes to the approved project. However, certain types
of past -award changes in budgets and projects shall require the prior trrinuff approval ofthe Service
Project Orficer, State, local, or Indian tribal governments must refer to 2 CFR 200.407 Prior ff'rilran
Approval, for additional information an the types of changes that require prior written approval.
Indirect/Direct Cast Transfers:
The transfer of amounts budgeted for indirect costs to cover an increase in direct costs and vice versus
requires prior written approval from the Service. Service approval orbudgel changes, such as changes
resulting From an increase in the Recipient's approved Indirect cost m1e, will depend on if funds are
available either from budgeted direct costs or through additional Federal funding. If funds are not
available the Service may, if not otherwise prohibited by legislation or regulation allow the Recipient to
use the excess indirect cost amount to satisfy, cost-sharing or matching requirements. However, the
excess amount may not be shifted to another Federal award unless specifically authorized by legislation.
Recipient must submit such budget change requests to the Service Project Officer.
Ms F114cam:a nevnlen 2 a&:ar2015 Pepe 5 of
Proicel Period Extensions:
lraddilianal time is needed to complete the approved project, you must send written notice, Significant
Development Report, to the Service Project Officer. This notice must be received by the Service Project
Officer at least 10 days berare the authorized project/budget period end date, and must include
supporting reasons and the revised project end date Extensions for time cannot be authorized for the
purpose ofspcnding an unused balance of funds that remains after the approved project activities have
been completed.
Proiccl Contacts:
this
AFO USFWS Kodiak Soil and Water Conservation District
4700 BLA1 Rd. 518 Marine Way, Suite 206
Anchorage, AK 99507 Kodiak, AK 99615
Telephone: 907-271-3764 Tel: (907) 486-5574
Email: rmnklin—dekker@rws.gov Fax: (907) 486-5586
Please contact Franklin Dekker with any questions, Please include the USFWS document number,
F13AC00878, assigned to this award in all written communications,
Sincerely,
KATHERINE rxs"�
SMILEY
u.. lat.aa Ilnl A++�
Katherine K. Smiley
Agreement Officer/Contnt:L Specialist
Division of Contracting and General Services
U.S. Fish and Wildlife Service/Region 7
Katharine Smilclnr%vs.rnv
907-786-3412
PNS F13AC0057B Revislcn 2 aG79.7015 Page 6 or
In Reply Refer To
AFW FO
GX/VI p ii- 6
'l---
-- iR
United States Department of the Interior `�"X--re
U.S. FISH AND WILDLIFE SERVICE
1011 East Tudor Road
Anchorage, Alaska 99503-6199
Blythe Brown
Pmject Coordinator
Kodiak Soil and Water Conservation District (KSWCD)
518 Marine Way, Suite 206
Kodiak, Alaska 99615
Tel: (907) 486-5574
Email: blythe.brown@kodiaksailandwater.org
DUNS: 130455475
Subject: Notice Cooperative Agreement Award F16AC01034
Dear Ms. Brown:
Your organization's application for Federal financial assistance titled' Kodiak Fish Passage
Improvements 2021" submitted to the U.S. Fish and Wildlife Service (Suvice)'s CFDA Program 15.608
is approved. This award has been assigned USFWS document number F16AC01034. This agreement is
entered into under the authority of the Fish and Wildlife Coordination Act (16 U.S.C. 661-667c; the Act
of lvtarch 10, 1934; Ch. 55; 48 Stat.401), the Fish and Wildlife Act (16 U.S.C. 742a -j, not including
742d -I; 70 Stat.l 119), and the Anadromous Fish Conservation Act (16 U.S.C. 757a -g; 79 Stat. 1125).
This award was announced on grants.gov under die following funding announcement number.
F16AS00041.This award is made based on Service approval of your organization's proposal si6med on
August 11, 3016 hereby included in this award Funds under this cooperative agreement award are to be
used to design and construct identified fish bamer culverts with fish -friendly culverts on at last one of
the listed 29 culverts within the Statement of Work. Options periods can be utilized to accomplished
additional fish passage projects on the list.
Under this award, the Recipient will:
Task t. Design, permit and bid at least 1 of the 29 Identified culvert replacements from higher to
lower priority, unless unexpected issues such as timing, other priorities or utility conflicts
prevent action and the next project in priority is attempted. The designs will employ stream
simulation principles and maximize fish passage while maintaining public safety, hydrologic
continuity and re -vegetation of disturbed area. It is intended that these designs include hydraulic
capacity and stream banks stable for up to the 100 -year flood event. All investigations, right-of-
way, permits and surveys are included in this task.
FWS DCN F16AC01034 06252016 Pope 1 ora
• Task 2. Construct the projects designed in the option years. Construction includes all inspections,
re -vegetation, and landscaping in compliance with 1311 permit stipulations.
• Task 3. Provide project management, biological surveying, maintenance and monitoring support
on the sites identified in the Statement of Work.
Under this award, the USFWS will:
Provide fish, habitat, hydrologic, hydraulic design, and bioengineering design expcnisc and
assistance to Kodiak Soil and Water Conservation District (KS WCD) for the duration of the
project.
Work collaboratively with KSWCD to create nt least one crossing that will maximize fish
passage and a provide quality control on design drawings that will be acceptable to permitting
agencies.
Answer field questions as trey arise during die construction process.
The project period or this atrard begins on August 15, 2016 through August 14, 2021. This is the
period of Federal sponsorship.
This award will be funded incrementally via a Notice of Award Change Letter (NOACL) for the
anticipated budget periods and funding amounts listed in the funding table. Prior to the end of the
successful perrarntnnce period of the current year the Recipient must request the next budget period
funding via a Significant Development Report (SDR). All required Perronnance and Financial Reports
must be submitted and accepted.
The fuoding period for the first segment or this project begins on August 15, 2016 through August
14, 2021. The total amount of Service funding available for Ole first segment of this project is 5185,000.
Only allowable costs resulting from obligations incurred during this funding period may be charged to
this award.
The Service's obligation to provide incremental funding up to the total anticipated award amount is
contingent on: 1) satisfactory Recipient performance and 2) the availability of funds. No legal liability
on the part of die Service exists unless and until the Service obligates funds and notifies the Recipient in
writing that funds are available for the purposes of this award.
The Service will revise this award over time to add new funding for each subsequent project segment.
Each project segment will be assigned s specific funding period, during which only allowable costs
resulting from obligations incurred during the specified funding period may be charged to this award.
All obligations incurred during a funding period must be liquidated no later than 90 calendar days of the
funding period end date, unless written authority to carry over unobligated funding is provided You
must submit a written request to the Service Project Officer before the end of the staled period ifyou
need more time to liquidate all obligations.
The Carryover of unabligated funding into the subsequent funding period is permitted, subject to the
Federal Appropriation Laws, with the written approval of the USFWS Project Officer. Each year of
funding has a specified period of availability. In the case of a balance of unused Funding at the end of
Fw3 oaN F154C01034 06252015 PA0e 2 a! 9
any specified funding period, except the final period of funding, the recipient may request for the
carryover orunobligated funds into the subsequent funding period by submitting a significant
development report (SDR) identifying the amount of unused funding and continued need to the USFWS
project officer for approval.
Project Performance Measurement:
The Recipient will be monitored for requires! Reporting; i.e. Performance Reporting, Financial
Reporting and all other Mandatory Reporting as identified in die Notice orAward Letter.
Additionally, the Project performance will be measured and evaluated by monitoring die Recipient's
successful completion of project activities, objectives, and deliverables as outlined in the following
scheduled tasks, which must be accomplished to achieve project success:
Perfarm,toce Ceals/Tasks project activities, objectives, and deliverables
Anticipated
Select consultants, conduct Gcldwork and surveys
Com lotion Date
October 30, 2016
Draft designs, specifications and cost estimate completed
November30, 2016
Final designs, specifications, cost estimate completed, permits obtained
March 31, 2017
Projects in -stream construction complete
July 15, 2017
Projects construction completed
October 1, 2017
Culverts that did not get done In 2017 -
Draft designs, specifications and cost estimate completed
November 30, 2017
Final designs, specifications, cost estimate completed, permits obtained
March 31, 2018
Projects in-strearn construction complete
July 15, 2018
Projects construction completed
October 1, 2018
Culverts that did not get done in 20 19 -
Draft designs, specifications and cost estimate completed
November 30, 2018
Finnl designs, specifications, cost estimate completed, permits obtained
March 31, 2019
Projects in -stream construction complete
July I5, 2019
Projects construction completed
October 1, 2019
Culverts that did not get done in 2019-
Draft designs, specifications and cost estimate completed
Nowembcr30, 2019
Final designs, specifications, cost estimate completed, permits obtained
March 31, 202D
Projects in -stream construction complete
July 15, 2020
Projects construction completed
October 1, 2020
Culverts that did not get done in 2020 -
Draft designs, specifications and cost estimate completed
November 30, 2020
Final designs, specifications, cost estimate completed, permits obtained
March 31, 2021
Projects in -stream construction complete
July 15, 2021
1. Projects construction completed
August 14, 2021
FV,S CCN- F16AC01034 OF., 5,7016 Page 3 at 9
The Recipient's project officer must immediately communicate (via telephone, fax or email) any
significant changes to (a) project objectives, (b) the above schedule, (c) approved budget, or (d) project
personnel, and then document these changes (along with an explanation ofwhy they occurred and
suggestions on how to deal with diem) in a Significant Development Report (SDR). Please sec the
Significant Development section of this award letter for details.
This award is funded as follows:
D er' tin f Action—
S VS
at
Award1
5185 000.00 1
52,200.00
Award Total; I
5185,00o,00 I
S2,200.00
Unfunded Budget Years Awarded: Subject to availability of funds and future government
appropriations:
-Budget Period 2: August 15, 2017—August 14, 3021
5350.000.00
S350,000.00
Budget Period 3: Au t I5, 2018 — Au st 14, 3021
$350,000.00
5350,000.00
Budget Period 4: August 15, 3019 — AuEst 14, 3021
$350,000.00
5350,000.00
Budget Period 5: August 15, 3020—
—August 14, 2021
S350,000.00
5350,000.00
Anticipated Award Total:
Sl 585 000.00
Sl 402 200.00
Federal SharefNfatch Reouirements:
The Federal share of the total project expenditures cannot exceed 99 percent Recipient is eligible to
request Federal obligated funds up to but not in excess of an amount equal to 99 percent of the total
project expenditures.
Svstem for Award Management ISAM) Rc istration:
Under the terms and conditions of this award, yourorganization must maintain an active SAM
registration at haps: www sam ury portal public SAM until the final financial report is submitted or
final payment is received, whichever is later. If your orgnnizotion's SAM registmtian expires during the
required period, the Service will suspend payment under this and all other Service awards to your
organization until you update your organization's SAM registration.
Terms of Acceptance:
Acceptance ofa financial assistance award (i.e., grantor cooperative agreement) from the Service
carries with it the responsibility to be aware of and comply with the terms and conditions applicable to
the award. Acceptance is defined as the start of wort:, drawing down funds, or accepting the award via
electronic means. Awards are based on the application submitted to and approved by the Service.
Awards are subject to the terms mud conditions incorporated into die notice of award either by direct
citation or by reference to the following: Federal regulations; program legislation or regulation; and
special award terms and conditions. The terms and conditions of Service awards flow down to
subrecipicnts and contractors, unless a particular award term or condition specifically indicates
otherwise. The Federal regulations applicable to Service recipients and their subrecipients and
contractors are listed by recipient type in the Service Financial Assistance Award Terms and
Conditions posted on the Internet at Into: www.fws eov eriuwg . If you do not have access to the
Internet and require a full text copy of the award terms and conditions, contact the Service Project
Officer.
FYb CCiJ FIBAC01034 D&25r01a Page 4019
If Recipient decides to not accept this award, Recipient must notify the Service Project Officer in
writing within 30 calendar days of that decision,
Prohibition on Issuing Financial Assistance Awards to Entities that Require Certain Internal
Confidentiality Agreements
Section 743 of Division E, Title VII of the Consolidated and Further Continuing Resolution
Appropriations Act of 2015 (Pub. L, 113-235) prohibits the use of funds appropriated or otherwise made
available under that or any other Act for grunts or cooperative agreements to an entity that requires
employees or contractors of such entity seeking to report fraud, waste, or abuse to sign internal
confidentiality agreements or statements prohibiting or otherwise restricting such employees or
contractors from lawfully reporting such waste, fraud, or abuse to a designated investigative or law
enforcement representative of federal department or agency authorized to receive such information.
Recipients must not require their employers or contractors seeking to report fraud, waste, or abuse to
sign internal confidentiality, agreements or statements prohibiting or otherwise restricting such
employees or contractors from lawfully reporting such waste, fraud, or abuse to a designated
investigative or law enforcement representative ora federal department or agency authorized to receive
such information.
Recipients must notify their employees or contractors that existing internal confidentiality agreements
covered by this condition are no longer in effect.
Special Conditions and Provisions:
Inadvertent Archeological or Flistorical Discoveries
In die event any archaeological or historic materials are encountered during project activity, work in the
immediate arm must stop and the following actions taken:
I. Implement reasonable measures to protect the discovery site, including any appropriate
stabilization or covering;
2. Take reasonable steps to ensure the confidentiality of the discovery sites; and
3. Take reasonable steps to restrict access to the site of discovery.
The recipient will notify the concerned Tribes and all appropriate county, state and federal agencies,
including the State Historic Preservation Office. Agencies and the Tribe(s) will discuss the possible
measures to remove or avoid cultural material, and will reach an agreement with the recipient regarding
actions to betaken and disposition ofmateriol. if Human remains are uncovered, appropriate law
enforcement agencies shall be notified first, and die above steps followed. If the remains are determined
to be Native, consultation with the affected Tribe(s) will take place in order to mitigate the final
disposition of said remains.
Liability and Insurance
The recipient or its sub -recipients will use equipment, vehicles, Hazardous materials, or otherwise
engage in high-risk activities during performance of the award that have the potential for claims to be
brought by third parties for death, bodily injury, property damage, or other loss.
Habitat Retention Period
The habitat retention period is defined as the period during which the landowner must allow the habitat
restored under this award to remain in place without interference. The habitat retention period is at least
10 years from NOAL project period start date, consistent with the terms of attached Partners for Fish
and Wildlife Landowner Agreement.
FNS DCN F15AC01034 c±.1512018 Page 5 of 9
Landowner Agreements
By accepting the terms of this Notice of Award Letter, Recipient agrees to coordinate with the Service
project officer to obtain signed Partners for Fish and Wildlife Program Landowner Agreement(s) for
sub -award recipients prior to initiating eligible habitat restoration work with a landowner(s). Signed
landowner agreements become part of the official project file.
Payments:
Your organization has completed enrollment in U.S. Treasury's Automated Standard Application for
Payment (ASAP) system. When requesting payment in ASAP, your Payment Requestor will be
required to enter an Account ID. The number assigned to this award is the partial Account ID in ASAP.
When entering the Account ID in ASAP, the Payment Requestor should enter the award number
identified in the subject line on letter followed by a percent sign (°G). Refer to the ASAP.gov Help
menu for detailed instructions on requesting payments in ASAP
Reaortine Requirements:
Financial and Performance Reporting Requirements:
Annual interim financial and performance reports and final financial and performance repons arc
required under this award. The report periods and due dates under this award are:
Report:
Report Period:
Report Due Date:
Interim financial report
August 15, 2016 - September 30, 2017
December 29, 2017
Interim performance report
August 15, 2016 -September 30, 2017
December 29, 2017
Interim financial report
August 15, 2016 - September 30, 2018
December 29, 2018
Interim performance report
October 1, 2017 - September 30, 2018
December 29, 2018
Interim financial report
August 15, 2016 - September 30, 2019
December 29, 2019
Interim performance report
October 1, 2018 -September 30, 2019
December 29, 2019
Interim financial report
August 15, 2016 -September 30, 2020
Dec ember29, 2020
Interim performance report
October 1, 2019 -September 30, 2020
December 29, 2020
Final Financial Report
August 15, 2016 - August 14, 2021
November 12, 2021
Final Performance Report
October 1, 2020 -August 14, 2021
November l2, 2021
Recipients must use the Standard Form (SF) 425, Federal Financial Reporr Comm for all financial
reporting. This form is available at hitp:H%ww.whitchouse.gov ornh grants-formsk
Performance reports must contain: 1) a comparison of actual accomplishments with the goals and
objectives of the award as detailed in the approved scope or work; 2) a description of reasons why
AVE DCN F16ACaiLL ear'SZate Page 6 al 9
established goals were not met, if appropriate; and 3) any other pertinent inforntation relevant to the
project results. Please include the Service award number provided in the subject line of this letter on all
reports.
Financial and performance reporting due dates may be extended by the Service upon receipt of a written
request addressed to the Service Project Officer identifying the type of report to be extended, the
requested revised due date, and o justification for the extension. The Service Project Officer may
approve an additional extension if justified by a catastrophe that significantly impairs the recipient's
operations. Requests for reporting due date extensions must be received by the Service Project Officer
no later than one day before the original reporting due dote.
All Financial and Performanee Reports must be sent to fiv7 to ccs «fws.gnv for review and
acceptance. DO NOT send the reports to the Service Project Officer; the reports will be
distributed to the appropriate individuals once received
Significant Developments Reports:
Events may occur between the scheduled performance reporting dates that have significant impact upon
the supported activity. In such cases, notify the Service Project Officer in writing as soon as the
following types of conditions become known:
• Problems, delays, or adverse conditions that will materially impair the ability to meet the
objective of the Federal award. This disclosure must include a statement of any corrective
oction(s) taken or contemplated, and any assistance needed to resolve the situation.
• Favorable developments that enable meeting time schedules and objectives sooner or at less cost
than anticipated or producing more or different beneficial results than originally planned.
QUI Significant Development Reports must be sent to the Service Project Officer
Other Reports or Deliverables:
Provide design documents for review including design drawings, hydrology, and hydraulic calculations
during the design process. Provide construction documents including drawings, specifications, cost
estimates, design reports, and bid sheets for culvert replacement projects. Provide as -built drawings for
culvert replacements in Aulocod Civil 3D and Adobe pdf format.
Deliverable
Submission InstructionsfDetailsDeliverable
E-mail to franklindekker;gf%vs.gov or provide
Due Date
Design Documents
During design
to Service Protect Officer on CO or DVD
Construction Documents
E-mail to franklin dekkenaiCws.gov orprovide
Prior to start of
to Service Project Officer on CD or DVD
construction
As -Built Drawings
E-mail to franklnn dekker@fws.gov or provide
90 days after
to Service Proiect Officer on CD or DVD
construction completion
All other deliverables must be sent to the Service Project Officer
AVS MN: FWAC01034 062312018 Page 7 of 9
Conflict of Interest Disclosures:
The recipient must establish safeguards to prohibit its employees and subrecipients from using their
positions for purposes that constitute or present the appearance of a personal or organizational conflict
of interest. The recipient is responsible for notifying the Grunts Officer in writing of any actual or
potential conflicts of interest that may arise during the life of this award. Conflicts of interest include
any relationship or matter which might place the recipient or its employees in a position of conflict, real
or apparent, between their responsibilities under die agreement and any other outside interests. Conflicts
of interest may also include, but are not limited to, direct or indirect financial interests, close personal
relationships, positions of trust in outside organizations, consideration of future employment
arrangements with a different organization, or decision-making affecting the award that would cause a
reasonable person with knowledge of the relevant facts to question the impartiality of the recipient
and/or recipient's employees and subrecipients in the matter.
The Grants Officer and the servicing Ethics Counselor will determine if a conflict of interest exists. If a
conflict of interest exists, the Grants Officer will determine whether a mitigation plan is feasible.
Mitigation plans must be approved by the Grants Officer in writing. Failure to resolve conflicts of
interest in a manner that satisfies the government may be cause for termination of the award.
Failure to make required disclosures may result in any of the remedies described in 2 CFR 200.338;
including suspension or debarment (see also 2 CFR part I80).
Potentially affecting this award. Non -Federal entities that have received a Federal award including the
term and condition outlined in 2 CFR 200, Appendix XII—Award Term and Condition for Recipient
Integrity and Performance blotters are required to report certain civil, criminal, or administrative
proceedings to SAM. Failure to make required disclosures can result in any of the remedies described in
2 CFR 200.338, Remedies far noncompliance, including suspension or debarment (See 2 CFR 200.113,
2 CFR Part 180, 31 U.S.C. 3321, and 41 U.S.C. 2313).
Project Plan and Budget Amendments:
Recipients are required to report deviations from budget or project scope or objective, and request prior
approvals (see 2 CFR 200.407 Prior written approvals) for budget and program plan revisions in
accordance with 2 CFR 200.303 Revision of budget and program plans, unless otherwise specifically
waived in this award.
Project Period Extensions:
If additional time is needed to complete the approved project, you must send written notice, Significant
Development Report, to the Service Project Officer. This notice must be received by the Service Project
Officer at least 10 days before the authorized project/budget period end date, and must include
supporting reasons and the revised project end date. Extensions for time cannot be authorized for the
purpose of spending an unused balance of funds that remains after the approved project activities have
been completed.
MS WN FIBAC01034 own,2DI6
PBaa 6 e19
rwluuuw uUn cr, nyarologlsr Blythe Brown, Project Coordinator
U.S. Fish and Wildlife Service Kodiak Soil and Water Conservation District 51 S
Anchorage Field OtTce Marine Way, Suite 206
4700 BLM Rd Kodiak, Alaska 99615
Anchorage, AK 99507 (907) 486-5574
907-271-3764 blythe_brown@kodiaksoilandwater.org
Please contact Franklin Dekker with any questions. Please include the assigned USFWS award number
F16AC01034 in all written communications.
Sincerely,
KATHERINE
SMILEY
Digitally signed by
KATHERINE SMILEY
Date: 2016.08.25 09:16:39
-08'00'
Katherine K Smiley
Agreement Officer/Contract Specialist
Division of Contracting and General Services
U.S. Fish and Wildlife Smice/Region 7
ntherincmilt r rws. Dov
907-786-3412
FWSOW F1aA001.634 6"125,72616 P ;p0e19
PPN Finalized: 8/11/1016
I. Project Title:
Kodiak Fish Passage Improvements 3021
Project Applicant Contact: (name, address, email, phone, fax, DUNS #)
Blythe Brown
Project Coordinator
Kodiak Soil and Water Conservation District (KSWCD)
518 W. Marine Way, Suite 206
Kodiak, Alaska 99615
Tel: (907) 486-5574
Email: ¢Iythc.brownekodiaksoilandwater or
DUNS: 130455475
it. Project Description
a. PurposclOoals
Kodiak Soil and Water Conservation District (KSWCD) encompasses over 3 million oars on
Kodiak Island and Southwest Alaska where human development is scattered in numerous coastal
communities. In Kodiak, AK and its surrounding communities a network of 0sh-bearing streams
and roads intersect. Table 1 contains the "Top 31" culverts that pose issues Cor salmon passage in
the Kodiak, AK arca that will be addressed in the future years under this agreement. KSWCD
plans to inspect, design, pemuil and construct at least one 0sh-friendly replacement to a fish
harrier identified within the "Top 31" culvert list. Should future modi0eatinns of this agreement
take place, Table 1 may be revised with the mutual consent of KSWCD and the Service to
account for new survey or cost data.
The top culvert identified for replacement is located upstream of Lake Orbin and its replacement
will build upon past wark by KSWCD, the Service and Kodiak Island Borough (KIB) to restore
salmon runs in the Russian River watershed. the beneficiaries of this project will be anacimmous
fish species within KSWCD. The coho, chum and sockeye salmon that historically spawned and
reared in the listed systems contributed to the commercial, sport and subsistence fisheries in the
lora! Kodiak area. These fisheries are an important facet of the local economy. Maybe more
importantly, these fish arc important food and fertilizer increasing productivity and biedivershy
on Kodiak Island. This project represents a mull -year commitment to improving salmon habitat
with the aim of healthier, more sustainable populations of pacific salmon on Kodiak Island.
Table 1. List of Culverts
ADFG
U/S
Est'
Owner -
NO'
Number
Miles
Wolershed
Dsgn.
ship
Solution
Stream Name
Road Name
Cost
3
207DOB52
Unnamed
Middle Bay Drive
0.25
Russian
$70,000
KID
Replace
Panamaroff Creek
2
20700855
NULL
Road
0.16
Panamaroff
$40,ODO
Kill
Re lace
Salonie Crk Rifle
3
20703099
Unnamed
Range Rd
0
Salonie
540,000
KID
Replace
Salonie Crk Rifle
4
20703100
Unnamed
Range Rd
0.13
Salanle
530,000
KID
Replace
Salonle Crk Rifle
5
20703101
Unnamed
Range Rd
0.13
Salonie
$70,000
KID
Replace
Salonle Crk Rifle
6
20703102
Unnamed
Range Rd
0.1
Salonie
S4D,OOD
KID
Replace
Satonle Crk Rifle
7
20703103
Unnamed
Range Rd
0.16
Salonie
$40,000
KID
Replace
Salonie Crk Rifle
8
20703104
Unnamed
Range Rd
0.17
Salonie
$40,000
Kill
Replace
9
20703109
Unnamed
Salonle Military Rd
0.1
Salonle
$0
KID
Remove
Unnamed Trib to
Natives
Boy Scout
of
10
20703471
(Genivieve) Lake
Abandoned
0.28
Buskin
$D
Kodiak
Remove
11
10103248
BatteryCreektrib
USGSBatte Rd
0.6
Buskin
540,000
USCG
Replace
12
10103253
Unnamed
Gunnery Drive
0.22
Buskin
$40,000
USCG
Replace
13
10103256
Unnamed
Magazine Access Rd
0.32
Buskin
540,000
USCG
Replace
14
1 10103259
1 Unnamed
Magazine Access Rd
0
Buskin
540,000
USCG
Replace
15
10103260
Unnamed
Burma Road
0.14
Buskin
$40,000
USCG
Ford
16
10103261
Unnamed
Access Road
0.19
Buskin
$40,000
USCG
Ford
USCG Base Access
17
20700786
Unnamed
Road
1.07
Buskin
570,000
USCG
Re lace
10
20700877
Unnamed
Tom Stiles Road
0.56
Buskin
$70,000
USCG
Replace
Unnamed
Tributary to
19
20703436
Buskin Lake
Old Military Rd
0.28
1 Buskin
$D
1 USCG
I Remove
Remove/Fo
20
20703437
Unnamed
Old Military Rd
0.25
Buskin
$2,000
USCG
rd
Remove/Fo
21
2070343B
Unnamed
Old Military Rd
0.19
Buskin
$30,000
USCG
rd
Natives
Boy Scout Lk
of
22
20703440
Outlet
Old Military Rd
0.81
Buskin
$7D,000
Kodiak
Re lace
23
20703470
Genivleve Creek
Abandoned
0.98
Buskin
$40,000
USCG
Remove
24
207D0810
259-24-1005217)
Chiniak High ay
0.81
Kalsin Bay
5100,000
AOOT
Replace
25
20700813
259-24-10048
Chiniak Highway
L06
Kalsin Bay
5100,000
ADOT
Replace
Black Canyon
Black
26
20700817
Creek
Chiniak Highway
1.06
Canyon
$100,000
ADOT
Replace
27
20700846
Virginia Creek
Monashka Bay Rd
3.14
Virginia
$100,000
ADOT
Replace
Shooting Range
28
10103255
Unnamed
Access Road
0.3
Buskin
540,000
USCG
Replace
29
10103254
I Unnamed
Gunnery Drive
0.1
Buskin
$40,000
USCG
I Replace
30
20700785
Unnamed
Anton Larsen Ba
0.19
Buskin
$100,000
USCG/D
OT
Replace
31
20703439
Unnamed
Old Military Road
0.1
Buskin
$40,000
USCG
Remove/Fo
rd
b. Tasks
Design and bid the culvert replacements as mutually identified and agreed upon with KSWCD, FINS,
and other stakeholders. For design and survey KSWCD will work with the Service to create scopes of
work and arrange contracting independently or through partnership with the Kodiak Island Borough
(KIB) as in past replacements. All projects selected will be reviewed by the Service during the draft
and final design phases. The designs will employ stream simulation principles and maximize fish
passage while maintaining public safety, hydrologic continuity and revcgetation of disturbed area. It
is intended that these designs include at least the bankfull width of the channel and stability for up to
the 100 -year flood event. All investigations, right -of --way, permits and surveys are included in this
task.
KSWCD and the Service will collaboratively seek agreements with culvert owners to maintain
completed projects for at least 10 years without interference, meaning that the project will stay in-
place and maintained to be free of debris without knowingly removing or damaging habitat
improvements. Example agreement shown in Attachment A.
Construct the projects in future Option Periods, as funding is made available. Per this agreement
scope, KSWCD intends to begin construction of culvert replacement in 2017 assuming funding is
available and KIB is ready. To accommodate unexpected delays, the original agreement will end
August 14, 2021. Future modifications of this agreement may complete at least one project a year
which will open the listed miles of the selected projects and is subject to the availability of funds over
the next 4 years.
Provide project management support during project prioritization, survey, design and construction.
Coordinate third party agreements with KIB when necessary.
Schedulelnroiect duration
The project schedule is as follows for original agreement:
• August 15, 2016 -August 14,2017. One culvert design completed minimum.
Subiect to availability of funds, the following schedule will be followed:
• August 15, 2011 -August 14, 2018. Next culvert completed minimum.
• August 15, 2018 -August 14, 2019. Next culvert completed minimum.
• August 15, 2019 -August 14, 2020. Next culvert completed minimum.
• August 15, 2020 -August 14, 2021. Next culvert completed minimum. Final Report.
c. Outcomes for original eareement
1. 0.25 miles upstream habitat opened
2. At least 1 of the 29 barriers removed.
d. Proiect deliverables
Deliverables will be per crossing:
Provide design documents for review including design drawings, hydrology, and hydraulic
calculations during the design process. Provide construction documents including drawings,
specifications, cost estimates, design reports, and bid sheets for culvert replacement projects. Provide
as -built drawings for culvert replacements in Autocad Civil 3D and Adobe pdf format.
Deliverable
Submission Instructions/Details
Deliverable Due Dale
Design Documents
E-mail to
During design
• 65% final design set, permits,
fmnklin_dekker@fws.gov or
Land. Structures ROW, appraisals. etc. (utilities)
cost estimates, technical specs
provide to Service Project Officer
• Bid document
on CD or DVD
Construction Documents
E-mail to
Prior to start of
• 100% final design set, permits,
franklin_dekker@fws.gov or
construction
cost estimates, technical specs
provide to Service Project Officer
Project inspection fees
on CD or DVD
As -Built Drawings
E-mail to
90 days alter
franklin—dekker@fws.gov or
construction completion
provide to Service Project Officer
Construction
on CD or DVD
2016 BUDGET (Based on an assumed estimate for design and construction of the first culvert.)
Cast Classification
FWS
Agreement
KSWCD
Match
(Other
Sources
Total
Costs
Administrative
Land. Structures ROW, appraisals. etc. (utilities)
Relocation expenses and payments
Architectural and engineering fees
S166.500
$166,5000
Other architectural and engineering fees
Project inspection fees
Site work
Demolition and removal
Construction
Equipment
Miscellaneous**
S18,500
IS2.200
$20,700
SUBTOTAL
5185.000
52,200
$187200
Contingencies
SUBTOTAL
$185,000
52.200
5187200
Project Income
TOTAL PROJECT COSTS
5185,000
$2.200
—
1 S187.205
*Costs may change based on actual design completion. This budget is only an estimate of costs
until an RFP for design is issued and a contract negotiated with a design consultant. Unused
design funds can be used for construction.
"Anticipated miscellaneous costs included project coordination, biological surveying, culvert
maintenance and monitoring.
Subsequent option years are requested to be funded up to $350,000 a year to achieve the desired metrics,
depending on funding availability.
Attachment A -- Blank Landowner Agreement
Landowner Agreement No:
Cost
Other:
[Use for Sub•uward Recipients -Le., landowners who will NO1 receive a Notice of Award letter front the
Partners Program. Landowners signing this document will work witlt a government or organizmion that
directly received a Notice of Award letter from USFWS.]
PARTNERS FOR FISH AND WILDLIFE PROGRAM
LANDOWNER AGREEMENT
Optional: Sub -Recipient Agreement to the Cooperative Agreement behreen the U.S. Fish
and Wildlife Service and [Government/Organization receiving a Notice of Award Letter]
This Landowner Agreement (Agreement), dated [Month / Day 1 Year], between (Landowner(s)], and
(Government/Organization receiving a Notice of Award Letter From the Partners Program],
[Coopemtor(s)], and the U.S. Fish and Wildlife Service (USFWS) is entered into pursuant to authority
contained in the Partners for Fish and Wildlife Act (P.L. 109.294), the Fish and Wildlife Coordination
Act (16 U.S.C. 661 et seq.) and the Fish and Wildlife Act of 1956 (16 U.S.C. 742a j), as amended. This
project was selected for funding because the Landowner(s) share(s) a common objective with the USFWS
to restore habitat for the benefit of Fcdcral trust species on private lands, and the project supports priority
actions identified in the Regional Partners for Fish and Wildlife (Partners) Program Strategic Plan.
[Name, Complete Address], hereby agrees to participate with the USFWS in conducting certain wildlife
management practices on lands owned or managed in [County, Borough, or Municipality Name], State of
[State Name], described as follows: all of, or within, (Township / Range / Section and/or Latitude /
Longitude and/or UTM).
In signing this Agreement, the Landowner(s) join(s) as a participant(s) in a wildlife habitat
improvement program and grant(s) to the Cooperators) and the USFWS authority to complete the
habitat improvement project or the Landowners) may personally carry out management activities with
financial or material support as described in attached Exhibit A. Any donation of supplies, equipment,
or direct payment from the Cooperator(s) to the Landowner(s) for carrying out the habitat
improvements is included in Exhibit A. The activities conducted pursuant to this Agreement are not to
replace, supplement or otherwise contribute to any mitigation or compensation that may be required of
the Landowner(s) or Cooperator(s), or other parties, as it result of any mandated requirements.
The term of this Agreement (also referred to as the habitat retention period) will [Select One: be
completed on [Month / Day / Year]. This Agreement may be modified at any time by mutual written
consent of the parties. It may be terminated by either party upon 30 days advance written notice to the
other party(ies). However, if the Landowncr(s) Icrminate(s) the Agreement berore its expiration, or if
the Landowner(s) should materially default on these commitments, then the Landowner(s) agrees) to
reimburse the Cooperator prior to final termination for the prorated costs of all habitat improvements
placed an the land through this Agreement, and the Cooperator will work with the USF%VS to determine
how those funds will be used. OR run concurrent with the existing USFWS easement on the property
and be subject to the terms and conditions of the easement regarding modificationhermination.] For
these purposes, the total cost or the habitat improvements to the United States is agreed to be 5
[XXX.M. (This total should tnmeh the amount in the budget table in Exhibit A).
Landowner:
The Landowner(s) or his/her land manager, with legal authority over land management decisions,
guaramcc(s) ownership of the above-described land and warrants that there are no outstanding rights that
interfere with this Landowner Agreement.
The Lnndowner(s) will notify the USFWS and other Cooperator(s) of planned or pending changes
in ownership. A change of ownership shall not change the terms of this Agreement. The
Agreement and terns shall be in effect on the described land for the term or the Agreement.
The Landowner(s) agrec(s) to allow access (with advance notice) to the USFWS and the other
cooperating partners) to implement the project described in Exhibit A, and to monitor project
success.
The Landowner(s) retain(s) all rights to control trespass and retains all responsibility for taxes,
assessments, and damage claims.
During the habitat retention period, the landowner(s) [Select one: must maintain the habitat restored
under this award OR must allow the habitat restored under this award to remain in place without
interference].
[Optional: expand on the meaning of"maintain the habitat restored." OR expand on the meaning of
"remain in place without interference."]
At the end of the habitat retention period, the habitat improvement project will become the sole property
and complete responsibility of the Landowner(s). There shall be no obligation to the USFWS after the
term of the Agreement has expired.
The Landowner(s) will be responsible for securing any necessary permits. [Optional: Technical advice
and support will be provided by participating agencies in the application for the permit(s)]. The
Landowners) and Coopemtor(s) agrees) to identify the USFWS' contribution to the project during
public presentations, reports, or other information published about the project, as appropriate.
Optional: The Landowner(s) will be free to remove any structure at his/her own expense at the
termination of the Agreement, however, the Agreement does not supersede any Local, Stale, or Federal
regulation that would apply to the removal of any such structure(s)].
[Optional: The Landowner(s) will not be responsible for replacing wildlife habitat developments that are
damaged or destroyed by severe acts of nature].
[Optional: if an USFWS casement is granted, the casement will supersede the provisions and terns of
this Agreement].
USFWS:
The USFWS will work with the Landowner(s) and Cooperator(s) signing this Agreement, throughout
the entire Agreement term to support actions needed to ensure dial The project is designed and
constructed per the Agreement and functions as intended.
The USFWS, its agents, or assignees will provide advanced notice prior to accessing the Landowner(s)
property to implement the project described in the work plan, and to monitor project success.
The USFWS assumes no liability for damage or injury other than that caused by its own negligence, on
the above acreage. The USFWS docs not assume jurisdiction over the premises by this Agreement.
Spatial Information Sharing: In accordance with the Privacy Act of 1974, permission must be
obtained from the Landowner(s) before any personal information can be released. The only information
that can be shared is payment information that is authorized by law. Therefore, Landowner(s) consent is
requested to allow for sharing of spatial information about this project solely with conservation
cooperators providing technical or financial assistance with the restoration, enhancement or
management of fish and wildlife habitat.
❑Me. the Landowner(s), consent to having spatial information about this project shared with
other conservation cooperators
❑Me, the Landowner(s), do NOT wish to have any spatial information about this project shared
with other conservation cooperators
Slenatures:
Name, Landowner(s) (Insert more signuture lines if needed) Date
Name, Cooperator(s) (insert more signature lines if needed) Dale
Name,
USFWS Partners Program Biologist Date
Name, USFWS Partners Program Stale Coordinator or Field Supervisor or Branch Chief
Date
EXHIBIT A
The habitat improvements described below are agreed to by [Landowner(s)], the USFW S, [and Other
Non -Governmental Organizations / Agency Partners (List All Titose providing Financial and/or
Technical Assistance)] in a Landowner Agreement dated [Month / Day / Year]. (This date must march the
beginning dale of tite Landowner Aereement.)
Description or Habitat Improvement Prolect and Objectives: (Aunch maps and drawings, as
applicable)
Describe, in detail, what is to be done in terns or habitat restoration, enimncement or creation of habitat
ori -the -mound. Specifically identify benefits to Federal must resources.
USF\VS will:
Describe in detail what the partners program Geld biologist is going to du (i.e., the substantial
involvement of the USFWS).
The LandownerW will:
Describe what Ihcy will provide in tcnus of financial or technical assistance lu the project.
t , K ■
Describe what financial or technical assistance contributions will be provided by the other cooperating
partners. Put N/A if there are none.
Additional Information as required for the ornlect:
Budeet Table:
'The total cost -share by the Cooperator(s), the USFWS, and the Landowner(s) must remain the same,
however allocations by category may be redistributed upon prior approval by the USFWS.
Any work to be completed may be modified with the mutual agreement of the aforementioned parties.
Meet Narrative.-
Describe
arrative:
Describe as needed any line items from the budget table above
Partners
Object Class
Landowner
USFWS
Partners Prograff
USFWS
Other Programs
Other
Non-USFWS
Totals
Personnel
S
S
S
S
S
$
S
$
S
S
S
S
S
S
S
S
S
S
$
S
E
S
S
$
S
S
S
S
S
$
SS
S
$
$
SS
S
S
S
S
Totals
S
S
S
I S
$
'The total cost -share by the Cooperator(s), the USFWS, and the Landowner(s) must remain the same,
however allocations by category may be redistributed upon prior approval by the USFWS.
Any work to be completed may be modified with the mutual agreement of the aforementioned parties.
Meet Narrative.-
Describe
arrative:
Describe as needed any line items from the budget table above
M REPLY REFER TO:
AFWFO
L.kNiu�T �'
run � •�wunx
United States Department of the Interior
U.S. FISH AND WILDLIFE SERVICE
1011 East Tudor Road
Anchorage, Alaska 99503-6199
Blythe Brown
Project Coordinator
Kodiak Soil and Water Conservation District (KSWCD)
518 Marine Way, Suite 206
Kodiak, Alaska 99615
DUNS: 130455475
Subject: Notice of Revision 402 to Financial Assistance Award F16AC01034
Dear Ms. Brown,
Your organization's request for award revision to U.S. Fish and Wildlife Service (USFWS) Award
F16AC01034 titled "Kodiak Fish Passage Improvements 2021"under CFDA #15.608; Fish Passage
Program is approved effective August 15, 2017. This award is revised as follows:
• This supplemental revision adds Budget Period 2 Funding to the existing award. Total funding
addition is 595,000.
• Under this revision the Kodiak Soil and Water Conservation District (TTCD) will:
o Task 1. Partner with Kodiak Island Borough to construct I fish passage project in 2018,
provided enough funds are available and Kodiak Island Borough is ready.
o Task 2. Provide project management, biological surveying, maintenance and monitoring
support on the sites identified in the Statement of Work.
Dales in the PPN and Performance Goal[fasks tables are updated to reflect completed work and
a delay in this culvert construction from 2017 to 2018.
The performance and budget period of this award remains as August 15, 2016 through August t4, 2021.
This is the period of Federal sponsorship.
The funding for Budget Period 2 begins on August 15, 2017 through August 14, 2021. The total
amount of Service funding available for this Budget Period 2 segment of the project is 595,000. Only
allowable costs resultine from oblieations incurred durine this funding oeriod and may be charged to
this award.
FWS DCN. F16AC01034 REV 02 0803 017 Page 1 of 11
This project will be funded incrementally via a Notice of Award Change Letter (NOACL) for the
anticipated future project periods and funding amounts listed in the funding table. Prior to the end of the
successful performance period of the current year the Recipient must request funding for the next project
period via a Significant Development Report (SDR). All required Performance and Financial Reports
must be submitted and accepted.
The Service's obligation to provide incremental funding up to the total anticipated award amount is
contingent on: l) satisfactory Recipient performance and 2) the availability of funds. No legal liability
on the part of the Service exists unless and until the Service obligates funds and notifies the Recipient in
writing that funds are available for the purposes of this award.
The Service will revise this award over time to add new funding for each subsequent project segment.
Each project segment will be assigned a specific funding period, during which only allowable costs
resulting from obligntions incurred during the specified funding period may be charged to this award.
All obligations incurred during a funding period must be liquidated no later than 90 calendar days of the
funding period end date, unless written authority to cant' over unobligated funding is provided .You
must submit a written request to the Service Project Officer before the end of the stated period if you
need more time to liquidate all obligations.
The Carryover of unobligated funding into the subsequent funding period is permitted, subject to the
Federal Appropriation Laws, with the written approval of the USFWS Project Officer. Each year of
funding has a specified period of availability. In the case of a balance of unused funding at the end of
any specified funding period, except the final period of funding, the recipient may request for the
carryover of unobligated funds into the subsequent funding period by submitting a significant
development report (SDR) identifying the amount of unused funding and continued need to the USFWS
project officer for approval.
Protect Performance Measurement:
The Recipient will be monitored for required Reporting; i.e. Performance Reporting, Financial
Reporting and all other Mandatory Reporting as identified in the Notice of Award Letter.
The following scheduled tasks have been revised and/or updated to reflect completed or new task. All
other project tasks; activities, objectives, and deliverables, set forth in the original award and any
previous revisions (modificationslamendments) are also applicable to, and are hereby incorporated by
reference into this revision.
Performance Goals/Tasks project activities, objectives, and deliverables
Anticipated
Completion Dale
Select consultants, conduct fieldwork and surveys
COMPLETED
Draft designs, specifications and cost estimate completed
COMPLETED
Final designs, specifications, cost estimate completed, permits obtained
COMPLETED
Projects in -stream construction complete
DELAYED TILL 2018
Projects construction completed
DELAYED TILL 20I8
Culverts that did not get done in 2017-
Dmfldesigns, specifications and cost estimate completed
REMOVED
Final designs, specifications, cost estimate completed, permits obtained
REMOVED
Projects in -stream construction complete
July 15, 2018
FWS DCN F16AC01034 REV 02 0&!0412017 page 2 of 11
Projects construction completed
October 1, 2018
Culverts that did not get done in 2018 -
Revision 402
(Budget Period 2: August 15, 2017 —August 14, 2021):
Draft designs, specifications and cost estimate completed
November 30, 2018
Final designs, specifications, cost estimate completed, permits obtained
March 31, 2019
Projects in -stream construction complete
July 15, 2019
Projects construction completed
October I, 2019
Culverts that did not get done in 2019 -
$280,000.00
Draft designs, specifications and cost estimate completed
November 30, 2019
Final designs, specifications, cost estimate completed, permits obtained
March 31, 2020
Projects in -stream construction complete
July 15, 2020
Projects construction completed
October 1, 2020
Culverts that did not get done in 2020 -
5350,000.00
Draft designs, specifications and cost estimate completed
November 30, 2020
Final designs, specifications, cost estimate completed, permits obtained
March 31, 2021
Projects in -stream construction complete
July 15, 2021
Projects construction completed
August 14, 2021
The Recipient's project officer must immediately communicate (via telephone, fax or email) any
significant changes to (a) project objectives, (b) the above schedule, (c) approved budget, or (d) project
personnel, and then document these changes (along with an explanation of why they occurred and
suggestions on how to deal with them) in a Significant Development Report (SDR). Please see die
Significant Development section of this award letter for details.
This award is funded es follows:
Description or Action
USFWS
Recipient
Revision 402
(Budget Period 2: August 15, 2017 —August 14, 2021):
595,000.00
52,000.00
Revision NO i, Administrative Revision addressing
Whistleblower Public Law
$0.00
50.00
Award
Budget Period 1: August 15, 2017 - Au st 14, 2021
S 185,000.00
52,200.00
Award Total:
$280,000.00
$4,200.00
Unfunded Budget Periods: Subject to availability of funds and future government
appropriations
Budget Period 3: August 15, 2018 — August 14, 2021
5350,000.00
5350,000.00
Budget Period 4: August 15, 2019 — August 14, 2021
5350,010.00
5350,000.00
Budget Period 5: August 15,2020—August 14, 2021
5350,000.00
5350,000.00
Anticipated Award Total
$1,330,000.00
1 $1,054,200.00
Terms of Acceptance:
All terms oracceptance to the original award and any previous revisions (modifications/amendments)
are also applicable to, and are Hereby incorporated by reference into, this revision. The Federal
regulations applicable to Service recipients and their subrecipients and contractors are listed by recipient
type in the Service Financial Assistance Award Terms and Conditions posted on the Internet at
httn://lewiv. fivs.gov/eranls:.
FWS DCN F16AC01034 REV 02 091042017 Page 3 of 11
NOTE: If your organization has conducted any lobbying this oast year you must Provide an SF -LLL no
response is rcouired if no lobbying activities have been conducted.
Special Conditions and Provisions:
All special conditions and provisions applicable to the original award and any previous revisions
(modifications/amendments) are also applicable to, and are hereby incorporated by reference into, this
revision.
Reportine Requirements:
Financial and Performance Reporting Requirements:
All reporting requirements as detailed in the original notice of award and any previous revisions
(modifrcations/amendments) are also applicable to and are hereby incorporated by reference into this
revision. See the following Annual reporting schedule:
Report:
Report Period:
Due Date:
Interim financial report
August 15, 2016 --September 30, 2017
-Report
December 29, 2017
Interim performance report
August 15, 2016 —September 30, 2017
December 29, 2017
Interim financial report
August 15, 2016 - September 30, 2018
December 29, 2018
Interim performance report
October[, 2017 -September 30, 2018
December 29, 2018
Interim financial report
August 15, 2016 -.September 30, 2019
December 29, 2019
Interim performance report
October 1, 2018 - September 30, 2019
December 29, 2019
Interim Financial report
August 15, 2016—September 30, 2020
December 29, 2020
Interim performance report
October 1, 2019 - September 30, 2020
December 29, 2020
Final Financial Report
August 15, 2016 —August 14, 2021
November 12, 2021
Final Performance Report
October I, 2020 — August 14, 2021
November l2, 2021
Recipients must use die Standard Form (SF) 425, Federal Financial Report form for all financial
reporting. This form is available at http://www.whiteliou5c.gov/omb/grants—fomis/.
Performance reports must contain: 1) a comparison of actual accomplishments with the goals and
objectives of the award as detailed in the approved scope of work; 2) a description of reasons why
established goals were not met, if appropriate; and 3) any other pertinent information relevant to the
project results. Please include the Service award number provided in the subject line of this letter on all
reports.
Financial and performance reporting due dates may be extended by the Service upon receipt of a written
request addressed to the Service Project Officer identifying the type of report to be extended, the
requested revised due dale, and a justification for the extension. The Service Project Officer may
FWS DCN: F16AC01034 REV 02 0070412017 Page 4 a111
approve an additional extension if justified by a catastrophe that significantly impairs the recipient's
operations. Requests for reporting due date extensions must be received by the Service Project Officer
no later than one day before the original reporting due dale.
All Financial and Performance Reports must be sent to fi0 fa cesa fws.eov for review and
acceptance. DO NOT send the reports to the Service Project Officer, the reports will be
distributed to the appropriate individuals once received.
Significant Developments Reports (SDR):
Events may occur between the scheduled performance reporting dates that have significant impact upon
the supported activity. In such cases, notify the Service Project Officer in writing as soon as the
following types of conditions become known:
• Problems, delays, or adverse conditions that will materially impair the ability to meet the
objective of the Federal award. This disclosure must include a statement of any corrective
action(s) taken or contemplated, and any assistance needed to resolve the situation.
• Favorable developments that enable meeting time schedules and objectives sooner or at less cost
than anticipated or producing more or different beneficial results than originally planned.
All SDRs must be sent to the Service Project Officer
Other Reports or Deliverables:
Provide design documents for review including design drawings, hydrology, and hydraulic
calculations during the design process. Provide construction documents including drawings,
specifications, cost estimates, design reports, and bid sheets for culvert replacement projects.
Provide as -built drawings for culvert replacements in Autocad Civil 3D and Adobe pdf format.
Deliverable
Submission
Deliverable Due Dote
Delivered and
Instructions/Details
Accepted Date
Design Documents
E-mail to
During design
franklin—dekker@fws.gov or
provide
to Service Project Officer on
CD or DVD
Construction
E-mail to
Prior to start of
Documents
franklin dekkerLfws.gov or
construction
provide
to Service Project Officer on
CD or DVD
As -Built Drawings
E-mail to
90 days after
franklin_dekkergRvs.gov or
construction
provide
completion
to Service Project Officer on
CD or DVD
All other deliverables must be sent to the Service Project Officer
FWS DCN, F16AC01034 REV 02 0810V2017 Page 5 W 11
Prosect Contacts:
The USFWS Prosect Officer for this award Is:
The Recipient Project Officer for this award is:
Franklin Dekker, Hydrologist
Blythe Brown, Project Coordinator
U.S. Fish and Wildlife Service
Kodiak Soil and Water Conservation District
Anchorage Field Office
518 Marine Way, Suite 206
4700 BLM Rd
Kodiak, Alaska 99615
Anchorage, AK 99507
(907) 486-5574
907-271-3764
blythe—brown@kodiaksailandwater.org
Franklin dekker fws. ov
The USFWS Grants.Officer for this award Is:
The Recipient Administration for this award Is:
Katherine K Smiley
Same as Recipient Project Officer
Agreement Officer/Contract Specialist
Division of Contracting and General Services
U.S. Fish and Wildlife Service/Region 7
Katherine snlilevulfilS.euc
907-786-3412
Please contact Franklin Dekker with any questions. Please include the assigned USFWS award
number F16AC01034 in all written communications.
Sincerely,
KATHERINE
SMILEY
Digitally signed by KATHERINE
SMILEY
Date: 2017.08.04 10:16:33
-08,00,
Katherine K Smiley,
Agreement Officer/Contract Specialist
Financial Assistance Office
Division of Contracting and General Services
Region 7, Alaska
U.S. Fish and Wildlife Service
FWS DCN F16AC01034 REV 02 06/042017 Page 6 of 11
REVISION 2 PPN Finalized: 5/412017
Project Title:
Kodiak Fish Passage Improvements 2021
Project Applicant Contact: (name, address, email, phone, fax, DIENS t{)
Blythe Brown
Project Coordinator
Kodiak Soil and Water Conservation District (KSWCD)
518 W. Marine Way, Suite 206
Kodiak, Alaska 99615
Tel: (907) 486-5574
Email: blvthc.brolvnGrkodiaksoilandwater.ora
DUNS: 130455475
Il. Project Description
a. Purpose/Goals
Kodiak Soil and Water Conservation District (KSWCD) encompasses over 3 million acres on
Kodiak Island and Southwest Alaska where human development is scattered in numerous coastal
communities. In Kodiak, AK and its surrounding communities a network of fish -bearing streams
and roads intersect. Table I contains the "Top 31" culverts that pose issues for salmon passage in
the Kodiak, AK area that will be addressed in the Future years under this agreement. KSIVCD
plans to inspect, design, permit and construct at lead one fish -friendly replacement to a fish
barrier identified within the "Top 31"culvert list. Should future modifications of this agreement
take place, Table I may be revised with the mutual consent of KSWCD and the Service to
account for new survey or cost data.
The lop culvert identified for replacement is located upstream or Lake Orbin and its replacement
will build upon past work by KSWCD, the Service and Kodiak Island Borough (KIB) to restore
salmon runs in the Russian River watershed. The beneficiaries of this project will be anadmmous
fish species within KSWCD. The coho, chum and sockeye salmon that historically spawned and
reared in life listed systems contributed to the commercial, sport and subsistence fisheries in the
local Kodiak arca Tliese fisheries are an important facet oFthe local economy. Maybe marc
importantly, these fish are important Food and fertilizer increasing productivity and biodiversity
on Kodiak Island This project represents a multi-year commitment to improving salmon habitat
with lite aim of healthier, more sustainable populations of pacific salmon on Kodiak Island.
FWS DCN FIBAC01034 REV 02 08/0412017 Page 7 or 11
Table I. List or culverts
FWS DCN'. F16AC01034 FEV 02 091642017 Page 8 01 11
ADFG
UIS
Owner-
No.
Number
MilesCost
Watershed
sn
ship
Solution
Stream Name
Road Name
1
20700852
Unnamed
Middle Say Drive
0.25
Russian
570,000
KIS
Replace
Panamaroff Creek
2
20700855
NULL
Road
OAS
Panamaroff
540,000
KIS
Replace
Salonle Crk Rine
3
20703D99
Unnamed
Range Rd
0
Salonle
540,000
KIS
Replace
Salonle Crk Rifle
4 120703100
Unnamed
Range Rd 1
0.13
Salonie I
530.000
KIS
Replace
Salonle Crk Rifle
5
20703101
Unnamed
Range Rd
0.13
Salonie
$70,GDO
KIS
Replace
Salonie Crk Rifle
6
20703162
Unnamed
Range Rd
0.1
Salonle
$40,000
KIB
Replace
Salonie Crk Rifle
7
20703103
Unnamed
Range Rd
0.16
Salonie
S40,000
KIB
Replace
Salonle Crk Rine
S
20703104
Unnamed
Range Rd
0.17
Salonie
540,1100
KIS
Replace
9
20703109
Unnamed
Salonie Military Rd
0.1 1
Salonie
5o
KIB
Remove
Unnamed Trib to
Natives
Boy Scout
of
30
20703471
IGenlvleve Lake
Abandoned
0,28
Buskin
Kodiak
Remove
11
10103246
BatteryCreek Crib
USGS BatteryRd
0.6
Buskin
b
USCG
Replace
12
10103253
Unnamed
Gunne Drive
0.22
Buskin
USCG
Re lace
13
10103256
Unnamed
Ma azine Access Rd
0.32
Buskin
USCG
Re lace
14
10103259
Unnamed
Ma azine Access Rd
0
Buskin
USCG
Re lace
15
10103260
Unnamed
Burma Road
0.14
Buskin
USCG
Ford
16
1 101032611
Unnamed
Access Road
0.19
Buskin
540000
USCG
Ford
USCG Base Access
17
20700786
Unnamed
Road
1.07
1 Buskin
$70,000
USCG
Replace
18
2070DS77
Unnamed
Tom Stiles Road
0.56
Buskin
570000
USCG
Replace
Unnamed
Tributary to
19
20703435
Buskin Lake
Did MilitaryRd
0.28
Buskin
$0
U5CG
Remove
Remove/Fo
20
20703437
Unnamed
Old Military Rd
0.25
Buskin
52,000
USCG
rd
Remove/Fo
21
20703438
Unnamed
Old Military Rd
0.19
Buskin
530,000
USCG
rd
Natives
Say Scout Lk
of
22
20703440
Outlet
Old Military Rd
0.81
Buskin
$70,000
Kodiak
Replace
23
20703470
Genivieve Creek
Abandoned
OAS
Buskin
540,000
USCG
Remove
24
20700810
259-24-10052 7
Chiniak Highway
0.81
Kaisln Say
5100,D00
ADOT
Replace
25
20700913
259.24.10048
Chlniak Highway
1.06
Kalsin Ba
5100 D00
ADOT
Replace
Black Canyon
Black
26
120700817
Cree
1.06
Canyon
$160,000
ADOT
Replace
27
207ODS46
!Virginia Creek
MHwRd
3.14
Virginia
51D0.000
ADOT
Replace
Shooting Range
28
10103255
1 Unnamed
Access Road
0.3
Buskin
540,000
USCG
Replace
FWS DCN'. F16AC01034 FEV 02 091642017 Page 8 01 11
29
10103254
Unnamed
Gunnery Drive
0.1
Buskin
S40.0D0
USCG
Re lace
3D
20700785
Unnamed
Anton Larsen Bay
0.19
Buskin
S1D0,000
USCG/D
OT
Replace
31
20703439
Unnamed
Old MilitaryRoad
0.1
Buskin
54D,DOD
USCG
Remove/fo
rd
b. Tasks
Design and bid the culvert replacements as mutually identified and agreed upon with KSWCD, FWS,
and other stakeholders. For design and survey KSWCD will work with the Service to create scopes of
work and arrange contracting independently or through partnership with the Kodiak Island Borough
(KIB) as in past replacements. All projects selected will be reviewed by the Scrvice during the draft
and final design phases. The designs will employ stream simulation principles and maximize fish
passage while maintaining public safety, hydrologic continuity and revegetation ofdisturbcd arca. It
is intended that these designs include at least the bankfuli width of the channel and stability for up to
the 100-ycar flood event. All investigations, right -of --way, perils and surveys are included in this
task.
KSWCD and the Service will collabomtivcly seek agreements with culvert owners to maintain
completed projects for at least 10 years without interference, meaning that the project will stay in-
place and maintained to be free of debris without knowingly removing or damaging habitat
improvements. Example agreement shown in Attachment A.
Construct the projects in future Option Periods, as funding is made available. KSWCD intended to
begin construction of culvert replacement in 2017, but will instead mise additional grant funds and
anticipate construction in 2018, assuming funds arc available and KIB is ready. To accommodate
unexpected delays, the original ugrecmcnl will end August t4, 2021. Future modifications of this
agreement may complete at least one project a year which will open the listed miles of the selected
projects and is subject to the availability of funds over the next 4 years.
Provide project management support during project prioritization, survey, design and construction.
Coordinate third party agreements with KIB when necessary.
Schedule/nmicci duration
The project schedule is as follows for original agreement:
• August 15, 2016—August 14, 2017. One culvert design completed minimum.
Suhiect to availability of funds. the fnllnwinu schedule will he followed:
• August 15, 2017 — August 14, 2018. One culvert construction completed minimum.
• August 15, 201 R — August 14, 2019. Next culvert completed minimum.
• August 15, 2019 — August 14, 2020. Next culvert completed minimum.
• August 15, 2020 —August 14, 2021. Next culvert completed minimum. Final Report
c. Outcomes for original asreement
1. 0.25 miles upstream habitat opened
2. Al least I of the 29 barriers removed.
d. Project deliverables
Deliverables will be per crossing:
Fws ON F16AC01034 REV 02 0aZ4/2D17 Page 9 Dr 11
Provide design documents for review including design drawings, hydrology, and hydraulic
calculations during the design process. Provide construction documents including drawings,
specifications, cost estimates, design reports, and bid sheets for culvert replacement projects. Provide
as-buill drawings for culvert replacements in Autacad Civil 3D and Adobe pdf format.
Deliverable
Submission Instructions/Details
Deliverable Due Date
Design Documents
E-mail to
During design
• 65% final design set, permits,
fmnklin_dekkcr@fws.gov or
Land, Structures, ROW, appraisais. ctc. (utilities)
cost estimates, technical specs
provide to Service Project Officer
• Bid dacumcnl
on CD or DVD
Construction Documents
E-mail to
Prior to start of
• 100% final design set, permits,
franklin_dckkcr@fws.gov or
construction
cost estimates, technical specs
Provide to Service Project Officer
Project inspection fees
on CD or DVD
As -Built Drawings
E-mail to
90 days atter
Franklin_dekkcr@fws.gov or
construction completion
provide to Service Project Officer
Construction
on CD or DVD
2017 BUDGET (Based on an assumed estimate for design and consiructinn orthe first culvert.)
Cost Classification
F%VS
Agreement
KSWCD
Match
(Other
Sources
Total
Costs
Administrative
Sources
Land, Structures, ROW, appraisais. ctc. (utilities)
Land, Structures, ROW, a sisals, cm.(utilities)
Relocation expenses and payments
9°
Architectural and engineering fecs
Other architectural and engincerina fecs
Project inspection fees
Site work
Demolition and removal
Construction
S85,500
S85,500
Equipment
Miscellaneous'
$9,500
S2,000
$11,500
SUBTOTAL
$95,000
52,000
$97,000
Contingencies
SUBTOTAL
595,000
$2,000
597,000
Project Income
TOTAL PROJECT COSTS
$95,000
$2,000
$97,OOD
*Anticipated miscellancnus costs included project coordination, biological surveying culvert
maintenance and monitoring.
REVISED 2016 BUDGET (Based on an assumed estimate for design and construction of the first
culvert.)
FNVS KSWCD
Total
Cost Classification Agreement Match
Costs
(Other
Sources
Administrative
Land, Structures, ROW, a sisals, cm.(utilities)
meats
9°
Architectural and engineering fees
sIFF 5aa
5123.5110••
PAF;59a
5123.500
Other architectural and cripincefing fees
Pro'ectinspection fees
Site work
Demolition and removal
Construction
543,000••
543,000
Equipment
Miscellaneous***
$18,500
$2200
$20,700
SUBTOTAL
$185000
$2.200
$187,200
Contingencies
SUBTOTAL
$185,000
$2.200
$187,200
Project Income
TOTAL PROJECT COSTS
$185.000
1 $2.200
$187,200
"Design fees for Middle Buy Drive and Battery Creek did not expend the entire design
budget. The remaining design budget was moved to construction according to Significant
Development Report received on 5/12017 and filed on 512/2017
""Anticipated miscellaneous costs included project coordination, biological surveying,
culvert maintenance and monitoring.
Subsequent option year, are requested to be funded up to $350,000 o year to achieve the desired metrics,
depending on funding availability.
FW5 DCN: FIGAC01034 REV 02 081042017 page 11 of 11
IN REPLY REFER TO:
AFWFO
C—XN13 ; D
...
nnn � wiuum
United States Department of the Interior •q'"`
U.S. FISH AND WILDLIFE SERVICE ,.
1011 East Tudor Road
Anchorage, Alaska 99503-6199
Blythe Brown
Project Coordinator
Kodiak Sail and Water Conservation District (KS WCD)
518 Marine Way, Suite 206
Kodiak, Alaska 99615
DUNS: 130455475
Subject: Notice of Administrative Revision 1103 to Financial Assistance Award F16AC01034
Dear Ms. Bmwn,
Administrative revision to U.S. Fish and Wildlife Service (USFWS) Award F16AC01034 titled "Kodiak
Fish Passage Improvements 2021" under CFDA # 15,608; Fish Passage Program is approved effective
August l5, 2017. This award is revised as follows:
• This administrative revision is to change the FWS funding provided with REV 03, no change
will be made to the amount. The funds will be de -obligated from the REV 02 funding line and
the funding will be provided with the new funding string under REV 03. All other terms and
conditions remain the same.
The performance and budget period of this award remains as August 15, 2016 through August 14, 2021.
This is the period of Federal sponsorship.
Proicct Performance Measurement:
The Recipient will be monitored for required Reporting; i.e. Performance Reporting, Financial
Reporting and all other Mandatory Reporting as identified in the Notice of Award Letter.
The following scheduled tasks have been revised and/or updated to reflect completed or new task. All
other project tasks; activities, objectives, and deliverables, set forth in the original award and any
previous revisions (modifications/amendments) are also applicable to, and are hereby incorporated by
reference into this revision.
FwS DCN F16AC01034 REV 03 081152017 Page 1 015
Performance Gaals/Tasks project activities, objectives, and deliverables
Anticipated
Completion Date
Select consultants, conduct fieldwork and surveys
COMPLETED
Draft designs, specifications and cost estimate completed
COMPLETED
Final designs, specifications, cost estimate completed, permits obtained
COMPLETED
Projects in -stream construction complete
DELAYED TILL 2018
Projects construction completed
DELAYED TILL 2018
Culverts that did not get done in 2017 -
$95,000.00
Draft designs, specifications and cost estimate completed
REMOVED
Final designs, specifications, cost estimate completed, permits obtained
REMOVED
Projects in -stream construction complete
July 15, 2018
Projects construction completed
October 1, 2018
Culverts that did not get done in 2018 -
Draft designs, specifications and cost estimate completed
November 30, 2018
Final designs, specifications, cost estimate completed, permits obtained
March 31, 2019
Projects in -stream construction complete
July 15, 2019
Projects construction completed
October 1, 2019
Culverts that did not get done in 2019 -
Draft designs, specifications and cost estimate completed
November 30, 2019
Final designs, specifications, cost estimate completed, permits obtained
March 31, 2020
Projects in -stream construction complete
July 15, 2020
Projects construction completed
October I, 2020
Culverts that did not get done in 2020 -
Draft designs, specifications and cost estimate completed
November 30, 2020
Final designs, specifications, cost estimate completed, permits obtained
March 31, 2021
Projects in -stream construction complete
July 15, 2021
Projects construction completed
August 14, 2021
The Recipient's project officer must immediately communicate (via telephone, fax or email) any
significant changes to (a) project objectives, (b) the above schedule, (c) approved budget, or (d) project
personnel, and then document these changes (along with an explanation of wiry they occurred and
suggestions on how to deal with them) in a Significant Development Report (SDR). Please see the
Significant Development section of this award letter for details.
This award is funded as follows:
Description of Action
USFWS
Recipient
Revision #03
$0.00
50.00
Change funding allocation, delete funding provided under
REV 02 and then add it back under the revised coding.
Revision #02
$95,000.00
$2,000.00
(Budget Period 2: August 15,2017—August 14, 2021):
Revision #01, Administrative Revision addressing
$0.00
50.00
Whistleblower Public Law
Award
I 5185,000.00
$2,300.00
PWS DCN F16ACaro34 REV 03 0611512G17 Page 2 015
Terms of Acceptance:
All terms of acceptance to the original award and any previous revisions (modifications/amendments)
are also applicable to, and are hereby incorporated by reference into, this revision. The Federal
regulations applicable to Service recipients and their subrecipients and contractors are listed by recipient
type in the Service Financial Assistance Award Terms and Conditions posted on the Internet at
http://wnvw. ftvs.uov/omnis/.
NOTE: if your oraanizetion has conducted any lobbying this past year you must Provide an SF -LLL, no
response is reguired if no lobbying activities have been conducted.
Special Conditions and Provisions:
All special conditions and provisions applicable to the original award and any previous revisions
(modifications/amendments) are also applicable to, and are hereby incorporated by reference into, this
revision.
Revortine Requirements:
Financial and Performance Revortine Requirements:
All reporting requirements as detailed in the original notice of award and any previous revisions
(modifications/amendments) are also applicable to and are hereby incorporated by reference into this
revision. See the following Annual reporting schedule:
Report:
Budget Period 1: August 15, 2017 - August 14, 2021
Report Due Date:
Interim financial report
August 15, 2016 - September 30, 2017
Award Total:
$280,000.00
1 S4,200.00
Unfunded Budget Periods: Subject to availability of funds and future government
appropriations
Budget
Period 3: August 15,2018 -August 14, 2021
S350,000.00T
5350,000.00
Budget
Period 4: August 15, 2019 - August 14, 2021
5350,000.00
$350,000.00
Budget
Period 5: August 15, 2020 -August 14, 2021
5350,000.00
5350,000.00
Interim financial report
Anticipated Award Total
_S1,330,000.00
I S1,054,200.00
Terms of Acceptance:
All terms of acceptance to the original award and any previous revisions (modifications/amendments)
are also applicable to, and are hereby incorporated by reference into, this revision. The Federal
regulations applicable to Service recipients and their subrecipients and contractors are listed by recipient
type in the Service Financial Assistance Award Terms and Conditions posted on the Internet at
http://wnvw. ftvs.uov/omnis/.
NOTE: if your oraanizetion has conducted any lobbying this past year you must Provide an SF -LLL, no
response is reguired if no lobbying activities have been conducted.
Special Conditions and Provisions:
All special conditions and provisions applicable to the original award and any previous revisions
(modifications/amendments) are also applicable to, and are hereby incorporated by reference into, this
revision.
Revortine Requirements:
Financial and Performance Revortine Requirements:
All reporting requirements as detailed in the original notice of award and any previous revisions
(modifications/amendments) are also applicable to and are hereby incorporated by reference into this
revision. See the following Annual reporting schedule:
Report:
Report Period:
Report Due Date:
Interim financial report
August 15, 2016 - September 30, 2017
December 29, 2017
Interim performance report
August 15, 2016 - September 30, 2017
December 29, 2017
Interim financial report
August 15, 2016 - September 30, 2018
December 29, 2018
Interim performance report
October 1, 2017 -September 30, 2018
December 29, 2018
Interim financial report
August 15, 2016 -September 30, 2019
December29, 2019
Interim performance report
October 1, 2018 - September 30, 2019
December 29, 2019
Interim financial report
August 15, 2016 - September 30, 2020
December 29, 2020
Interim performance report
October 1, 2019 - September 30, 2020
December 29, 2020
FWS DCN FIBAC01034 REV 03 081152017 Page 3 of 5
Einal Financial Report
August 15, 2016—August 14, 2021
November 12, 2021
Final Performance Report
October 1,2020—August 14, 2031
November 12, 2021
Accepted Date
Design Documents
Recipients must use the Standard Form (SF) 425, Federal Financial Report form for all financial
reporting. This form is available at http://www.whitehouse.gov/omb/grants—forms/.
Performance reports must contain: 1) a comparison of actual accomplishments with the goals and
objectives of die award as detailed in the approved scope of work; 2) a description of reasons why
established goals were not met, if appropriate; and 3) any other pertinent information relevant to the
project results. Please include the Service award number provided in the subject line of this letter on all
reports.
Financial and performance reporting due dates may be extended by the Service upon receipt of a written
request addressed to the Service Project Officer identifying the type of report to be extended, the
requested revised due date, and a justification for the extension. The Service Project Officer may
approve an additional extension ifjustified by a catastrophe that significantly impairs (lie recipient's
operations. Requests for reporting due date extensions must be received by the Service Project Officer
no later than one day before the original reporting due date.
All Financial and Performance Reports must be sent to fw7 fa ces(alfivs.Eov for review and
acceptance. DO NOT send the reports to the Service Project Officer; the reports will be
distributed to the appropriate individuals once received.
Significant Developments Reports (SDR):
Events may occur between the scheduled performance reporting dates that have significant impact upon
the supported activity. In such cases, notify the Service Project Officer in writing as soon as the
following types of conditions become known:
• Problems, delays, or adverse conditions that will materially impair the ability to meet the
objective of the Federal award. This disclosure must include a statement of any corrective
action(s) taken or contemplated, and any assistance needed to resolve the situation.
• Favorable developments that enable meeting time schedules and objectives sooner or at less cost
than anticipated or producing more or different beneficial results than originally planned.
All SDRs must be sent to the Service Project Officer
Other Reports or Deliverables:
Provide design documents for review including design drawings, hydrology, and hydraulic
calculations during die design process. Provide construction documents including drawings,
specifications, cost estimates, design reports, and bid sheets for culvert replacement projects.
Provide as -built drawings for culvert replacements in Autocad Civil 3D and Adobe pdf format.
Deliverable
Submission
Deliverable Due Date
Delivered and
Instructions/Dctnils
Accepted Date
Design Documents
E-mail to
During design
Franklin dekker fws. ov or
FWS DCN FISAC01034 REV 03 081152017 Pape 4 el 5
All other deliverables must be sent to the Service Project Officer
Project Contacts:
The USFWS Project Officer for this award Is:
provide
to Service Project Officer on
CD or DVD
Franklin Dekker, Hydrologist
Blythe Brown, Project Coordinator
Construction
E-mail to
Prior to start of
518 Marine Way, Suite 306
Documents
franklin_dekker@fws.gov or
construction
(907) 486-5574
907-371-3764
provide
Franklin dekkerAlws.gov
The USFWS Grants Officer for this award is:
to Service Project Officer on
Katherine K Smiley
Same as Recipient Project Officer
Agreement Officer/Contract Specialist
CD or DVD
Division of Contracting and General Services
As -Built Drawings
E-mail to
90 days after
907-786-3413
franklin_dekker@fivs.gov or
construction
provide
completion
to Service Project Officer on
CD or DVD
All other deliverables must be sent to the Service Project Officer
Project Contacts:
The USFWS Project Officer for this award Is:
The Recipient Project Officer for this award is:
Franklin Dekker, Hydrologist
Blythe Brown, Project Coordinator
U.S. Fish and Wildlife Service
Kodiak Soil and Water Conservation District
Anchorage Field Office
518 Marine Way, Suite 306
4700 BLM Rd
Kodiak, Alaska 99615
Anchorage, AK 99507
(907) 486-5574
907-371-3764
blythe_brown@kodiaksoilandwater.org
Franklin dekkerAlws.gov
The USFWS Grants Officer for this award is:
The Recipient Administration for this award is:
Katherine K Smiley
Same as Recipient Project Officer
Agreement Officer/Contract Specialist
Division of Contracting and General Services
U.S. Fish and Wildlife Service/Region 7
Katherine smiicyarws.eov
907-786-3413
Please contact Franklin Dekker with any questions. Please include the assigned USFWS award
number F16ACO1034 in all written communications.
Sincerely,
Digitally signed by KATHERINE
KATHERINE SMILEY SMILEY
Date: 2017.08 15 12:19:26.06'00'
Katherine K Smiley,
Agreement OfftceriContract Specialist
Financial Assistance Office
Division of Contracting and General Services
Region 7, Alaska
U.S. Fish and Wildlife Service
FWS DCN F16AC01034 REV 03 081152017 Pape 5 o15