1997-06-10 Special MeetingKODIAK ISLAND BOROUGH
Special Assembly Meeting
June 10, 1997
A special meeting of the Kodiak Island Borough
Assembly was held June 10, 1997 in the Assembly
Chambers of the Kodiak Island Borough Building,
710 Mill Bay Road. The meeting was called to order
at 7:30 p.m.
There were present:
Robin Heinrichs,
Tom Abell
Bob Johnson
Gary Stevens
Jerome Selby, Mayor
Donna Smith, CMC /AAE, Clerk
Presiding
Tuck Bonney
Mike Milligan
Wayne Stevens
comprising a quorum of the Assembly; and
Presiding Officer Heinrichs recessed the regular
meeting to convene to the hearing.
1. Hearing on Contract Dispute Resolution in the
Matter of MKB Constructors, J.V. v. The Kodiak
Island Borough.
A. Legal Representative for MKB Constructors,
J.V.
B. Michael Schestopol, representing MKB Constructors,
J.V. on the Peterson Elementary School remodel
project, elected to not address specifics as Mr. Beck
covered them in considerable detail in the findings
and conclusions that were rendered after three days
of his review. In addition, there were in excess of
200 pages of trial and pre- hearing documents. Mr.
Beck was proposed by the Borough and nominated in the
Assembly's stead. Mr. Schestopol's office had
experience with Mr. Beck, who had been adverse to the
firm and, therefore, objected to the appointment of
Mr. Beck and lost. MKB's complaints were a result of
GDM, the architect.
Mr. Schestopol was present to relay the position of
MKB and their willingness to abide by and accept the
findings and conclusions with no intention to appeal.
He presented a history of the project. The contract
was bid in December, 1993, awarded on December 20,
1993, and work commenced on January 14, 1994. The
school opened August 30, 1994 with final completion
Special Assembly Meeting
June 10, 1997
REGULAR MEETING
ROLL CALL
HEARING
Volume XXII
Page 258
of the project in October, 1994. Additional requests
for change orders were submitted; some were paid,
others were not. An appeal in April 1995 was
presented to Mayor Selby. Due to a lack of response
from the Borough and the architect, in August 1995
MKB filed suit for the contract balance, retention,
and change orders. In October 1995, the Borough
answered interrogatories under oath stating all sums
due were paid. Upon discovery in June 1996, the
judged ruled arbitration or the case would be sent
back to the Assembly; the Borough declined to
arbitrate so the case was referred to the Assembly.
The Borough appointed Mr. Beck, to whom MKB objected,
but was disallowed.
Mr. Schestopol enumerated the issues and dollar
amounts claimed by MKB to be considered. Because it
had been two years and three months since the school
was completed, Mr. Beck also found that MKB was
entitled to additional amounts of $83,508, interest
since June 1, 1995, and additional interest of
$58,947. MKB has not been paid. There was no way
MKB would come out whole with attorney fees,
discovery costs, etc. Now was the time to settle as
the Borough had possession of the school with no
warranty claims. He urged adoption of the findings
of fact and conclusions of law.
Responding to Assemblymember G. Stevens,
Mr. Schestopol said his comment that MKB would not be
whole was because the award was not what MKB thought,
and there were additional attorney fees and discovery
costs. He remained to answer further questions.
B. Legal Representative for Kodiak Island
Borough.
Joel Bolger, Borough attorney, recommended the
Assembly adopt the findings of fact and conclusions
of law proposed by Mr. Beck as the issues were
debated and litigated. There was $187,000
representing money in the original contract, $155,068
representing retainage, and $32,416 representing
change orders unpaid at the time of the dispute.
After reviewing the change orders, the consultant
suggested the Borough pay an additional $65,875. The
Borough proposed payment to MKB in June of 1996; MKS
declined at that time. Mr. Bolger recommended
payment of the approximately $83,000 interest as
recommended by the hearing officer
Mr. Bolger focused on the delay claim. There was a
short timeframe to complete the remodel contract.
The hearing examiner identified a two month delay of
Special Assembly Meeting
June 10, 1997
Volume JLXII
Page 259
initial site work and execution of additional masonry
on new addition. The hearing officer found MKB was
attributable to the approximately 54 days behind
schedule June 1. There were problems with the boiler
in the school that needed repairing; however, the
hearing officer discovered this did not delay the
sheetrock work and, therefore, found no additional
compensation was due.
Another substantial delay was in response to a
submittal for hollow metal door frames that the
architect did not respond to for 90 days. There was
warranty in the contract that there would be a 30 day
turn around to which the architect did not adhere for
this submittal. This was responsible for the period
that preceded the substantial completion. This delay
was the primary basis for the finish work delay. The
hearing officer found MKB should be paid.
The hearing officer also noticed a design flaw in the
height of existing wall in the plans. The plans
tended to show the existing exterior wall was two
feet higher than actual. Although the hearing
officer found MKB should have pre- verified the
measurement, there were related designs attributable
to the architect for an eight day delay.
Mr. Bolger summed up the substantial delays
attributed to MKB architect GDM. After calculation,
the hearing officer determined the award of a portion
of the overtime, inefficiency when the project needed
to be speeded up, and additional amount of overhead
for a sum of approximately $83,000 additional costs
to the Borough. The hearing officer recommended no
award on other items outlined and detailed.
In summary, the hearing officer recommended an
$407,186.13 award to the contractor to include the
original amount, change orders, and interest.
Responding to inquiries from Assemblymembers W.
Stevens, G. Stevens, and Bonney, Mr. Bolger said MKB
asserted they would pay the subcontractors. He spoke
of the approval of two party checks to pay the
subcontractors that MKB declined to accept. The
process for the subcontractors would be to file
claims against MKB if they were not paid.
Responding to Assemblymember W. Stevens, Mr. Bolger
noted the pending claim against GDM included all
items attributed in the hearing officer's decision.
Special Assembly Meeting Volume IOC
Tune 10, 1997 Page 260
2. Executive Session EXECUTIVE
SESSION
A. Consideration of the Hearing Examiner's
Proposed Findings of Fact and Conclusions
of Law in the Matter of MKB Constructors,
J.V. v. the Kodiak Island Borough.
G. STEVENS,
seconded by MILLIGAN
VOTE ON MOTION
Ayes:
Noes: Johnson
Special Assembly Meeting
June 10, 1997
move to convene into
executive session for
consideration of the
hearing examiner's
proposed findings -of-
fact and conclusions of
law in the matter of
MKB Constructors, J.V.
versus the Kodiak
Island Borough.
Assemblymember G. Stevens felt a need to discuss the
findings and conclusions with the Borough attorney.
Asked to respond, Mr. Bolger felt it was not
appropriate for him to appear in the executive
session because, as an advocate of the Borough's
position, he would not be able to advise. He was
available to answer questions in open session.
Assemblymember Milligan supported the motion because
the process was not normal and state law allowed the
assembly to convene into executive session on items
pertaining to litigation. Also, because he still was
concerned about the impact to local contractors,
executive session would allow discussion in detail.
Assemblymember G. Stevens understood the attorney's
comments but felt it was important to discuss this
with Mayor Selby.
Abell, Bonney,
Milligan, G. Stevens,
W. Stevens, Heinrichs
MOTION CARRIED 6 ayes, 1 no
Presiding Officer Heinrichs recessed the regular
meeting and convened into executive session at 8:06
p.m. At 8:24, he reconvened the regular meeting and
closed the hearing at 8:25 p.m.
Volume XXII
Page 261
4. Resolution No. 97 -23 Adopting Findings of Fact RESOLUTION
and Conclusions of Law in the Matter of MKB NO. 97 -23
Constructors, J.V. v. the Kodiak Island Borough.
JOHNSON, moved to adopt
seconded by MILLIGAN Resolution No. 97 -23.
Assemblymember Johnson thought it was a good
settlement as a result of the hearing testimony.
VOTE ON MOTION
Ayes:
Noes: None.
MOTION CARRIED Unanimous
There being no further business to come before the ADJOURNMENT
Assembly, the meeting adjourned at 8:28 p.m.
ATTEST:
( 02 lif1 }2 C
Donna F. Smith, CMC /AAE
Borough Clerk
Special Assembly Meeting
June 10, 1997
Bonney, Johnson,
Milligan, G. Stevens,
W. Stevens, Abell,
Heinrichs
Robin Heinrichs
Presiding Officer
Approved: 07/17/97
Volume XXII
Page 262