1985-85 Adopting A Capital Improvement Program For Fiscal Year 1987 Through 1991 And Establishing Capital Project Priorities.KODIAK ISLAND BOROUG
RESOLUTION NO. 85 -85 -.
A RESOLUTION OF THE KODIAK ISLAND BOROUGH ASSEMBLY ADOPTING A CAPITAL
,IMPROVEMENT PROGRAM FOR FISCAL YEAR 1987 THROUGH 1991 AND ESTABLISHING CAPITAL
PROJECT PRIORITIES.
WHEREAS, a Five -Year Capital Improvement Program has been prepared by
'the Borough for fiscal years 1986 through 1991, and
WHEREAS, the Borough's Planning and Zoning Commission has recommended
approval of the prioritized FY 87 capital improvement priorities at its meeting
;in accordance with Borough Code Section 2.24.030 (e), and
WHEREAS, the Borough Assembly held a public hearing on the Five -Year
Capital Improvement Program including the priorities during its meeting on
October 3, 1985.
NOW, THEREFORE, BE IT RESOLVED that the document entitled "Kodiak
Island Borough Capital Improvement Program" for the years from July 1, 1986
through June 30, 1991 is hereby adopted by reference, and
Borough Clerk
BE IT FURTHER RESOLVED that the Borough's capital project priorities
for FY 1987 are as follows:
1. Fisheries Technology Center $ 8,500,000
2. Hospital Construction 15,600,000
3. Solid Waste Disposal Site 2,000,000
4. School Repair, Addition /Upgrade East Elementary,
High School, Larsen Bay, Old Harbor, Port Lions,
Peterson, Baranof Track 13,440,000
5. St. Hermans Bay Permanent Breakwater 26,659,790
6. Cold Storage Facility A&E 500,000
7. Cape Chiniak Road Erosion /Relocation 350,000
8. Kitoi Bay & Karluk Hatcheries Improvements 400,000
9. Borough Developmental Disabilities & Student
Housing /Upgrade 250,000
10. Service District #1 Water & Sewer Projects 4,900,000
11. Sargent Creek /Birch Circle 900,000
12. Left Turn Lanes at Airport & Base 800,000
13. Kodiak Comm Coll Health & Science Bldg A &E /Phase I 3,800,000
14. State Airport Expansion /Upgrade 5,000,000
15. Mill Bay Reconstruction A &E Cutoff Road to Y 2,600,000
16. Sharatin /Perenosa Construction 3,000,000
17. Airport Runway Lighting Project 956,000
18. Airport Sewage Treatment Plant 1,500,000
19. Kalsin Hill Road Relocation 3,900,000
20. Runway 18 -36 Resurfacing 2,512,000
21. DOT Maintenance Facility 4,500,000
BE IT FURTHER RESOLVED that Borough administration is hereby
instructed to advise the governor, legislature and appropriate state agencies
of the Capital Improvement Program and priorities adopted by the Borough
Assembly.
PASSED AND APPROVED this 3rd day of
ATTEST:
October
, 1985.