FY2023-37 Kodiak High School Roof Repairs With Rain Proof Roofing Of AnchorageRain Proof Roofing 2201 East 84'" Court 1255 West Winter Court Contract FY2023-37
Anchorage,) 3 4-554 WasPhone:
AK 99654
Phone: (907) 344-5545 Phone: (907) 373-5545
,Y//d L Fax: (907)349-3386 Fax: (907)373-5509
RPR, Inc. dba Rain Proof Roofing
December 15, 2022
Kodiak Island Borough
Attn: Patricia Valerio
710 Mill Bay Road
Kodiak, AK 99615
Re: Kodiak High School — Roof Replacement
Subject: Bid Proposal
Dear Madam:
We propose to provide all labor, material and equipment to install per the Work described below:
Roof Replacement: Remove and Replace PVC Roof System at Water Damaged Roof Area with new PVC
Fully Adhered Roof System to match existing. See Attached Aerial View to clarify specific area.
• Remove existing coping and base flashings and salvage for reinstallation.
o If base flashings require removal of siding, then Existing PVC will be trimmed below base
flashing and new PVC roofing will be flashed onto existing.
• Install 5/8" Dens Deck Sheathing mechanically attached to structural deck.
• Install Self Adhering Membrane, primed and adhered to sheathing.
• Install 1/4" per Foot Type II Tapered EPS Insulation in 2 Layers, thickness at Drains to Match existing.
o Insulation to be Adhered with Manufacturer's 2 Part Urethane Adhesive.
• Install 5/8" Dens Prime Cover Board, adhered with Manufacturer's 2 Part Urethane Adhesive.
• Install Carlisle "Gray" 80 Mil PVC Fully Adhered Roof System.
• Install Carlisle PVC Walk Pad in similar locations as existing.
• Install Salvaged Coping and Base Flashing.
• Provide Installer's 2 Year Standard Labor and Material Warranty.
• Provide Manufacturer's 20 Year Standard Labor and Material Warranty.
Scope Clarifications:
• Work Schedule: June or July 2023
• Estimated Duration Onsite: 3 Weeks
• Project Based on SOA Title 36 Wage Determination.
• Project Resources Supplied by Contractor.
o Ground Level Forklift for Material Handling.
o Crane or Roof Hoist for Placing Material At Roof Level.
o Dumpster
o Porta — Can
• Project Resources Supplied by Owner.
o 1000 sf of Laydown Area near roof access.
All material FOB jobsite and installed.
We exclude the following:
• Carpentry or structural work
• Snow or ice removal
• Cost of bond (1.5%), Local Taxes
Lump Sum Base Bid: $ 235,000.00
Proposal valid for thirty (30) days.
We specifically exclude all design or professional services.
Proposal based on the issuance of an acceptable subcontract such as AGC 655.
Please contact us if you have any questions.
Respectfully submitted,
GGA- ,4�� PAY P Red -4y
Rain Proof Roofing
info(a)rainproofroofing.com • www.rainproofroofing.com