1994-07-12 Regular Meeting Q ARCHITECTURAL REVIEW BOARD
MINUTES
July 12, 1994
2 . CALL TO ORDER
The meeting was called to order at 7 : 00 p. m. by, Woody Koning,
Chairman, in the Conference Room.
II . ROLL CALL
Members Present Members Absent Staff Present
Woody Koning Eric Ness Connie Lanahan
Ed Mahoney John Burt
Scott Bonney Gerry Cloudy Staff Absent
Greg Hacker Steve Hobgood
Betty Walters
Kyle Schaffer
Also attending was Stu Smith , Architects Alaska .
A quorum was established .
III . APPROVAL OF MINUTES
Minutes of the June 21 , 1994 meeting were unanimously approved
following a motion made by Scott Bonney and a second by Kyle
Schaffer.
IV. OPEN MEETING ACT
The pamphlet LAWS OF ALASKA 1994 was passed out for members to
review. Betty Walters explained that some of the laws have been
clarified concerning holding open meetings of governmental bodies
and that all members should read the pamphlet .
V. NORTHSTAR
The 95% drawings and specs were issued for review. The comments
made were as follows:
Koning -
Woody commented that he has a problem with our process of
reviewing the drawings . He is sure the architect will catch some
of his comments and he would prefer to review a set of drawings
that were ready to go on the street to save him time from doing
the work the architect is going to be doing .
Mr . Smith stated that approval is a formality that the ARB does,
review and comments is a valuable service the ARB does .
` •
, `
Prints-
AS Category 2 Sheet 1
�� Vestibule 100 shown as 101
Hallway 103B should be l04B
2/2 Wall type 15 grid line E52 . 5 has double sheet rock for
sound deadening. Nurse's office and conference rm. shows 14 /
should be changed to 15 .
3/2 Vestibule 100 called out elevations
Clarify corridor cap outside teachers workroom
Category 2 Sheet 6
Delete drop ceiling in gym storage
Category 4 Sheet 4 37 /4
Detail 32/4 is wrong
25/5 . 3 Can't get someone in there to hang rock
Finish schedule
Workroom 107 N, W & S (CMU) , E (GWB)
109 toilet-ceiling suspend acoustical tile
top of walls butting ceiling should be L metal edge, no
reveal
table/chair storage 114 E & W wall show GWB, should be CMU
Specs-
He has a concern over the paperwork return. It needs to be in a
timely manner. Submittals need to be gone over with Borough
people . There should be a 14 day turn around time .
Section 09900
Exterior siding painting EPS4 , 1 coat shop/1 coat field
����N Add top of wall detail w/out reveal
��
�=' Omcber- Prints changes
1/1 Add fence to North end of fuel tank enclosure.
Add man and vehicle gate to fuel tank enclosure.
Move transformer into South end of fuel tank enclosure .
Add dumpster site outside of fenced area by fuel tank.
Include bollards as required.
Move man gate on end of NE wing closer to front of building
and reconfigure vehicle trap.
1/6 Detail 30/ 1 taper flagpole base small top to large bottom.
2 /5 Detail 7/2 did we provide for hanging a swing in the Alt
OT/PT room or in the commons?
2 /6 Match relief air hood configuration to 3/1 and 9/4 .
2/9 Mech room roof access hatch needs to be relocated south to
head of stairs and turned 90 degrees so ladder is against
mau.
Show curbs for boiler/HWH stacks and exhaust fan?
8/8 Label HWC return cross-connect valve "NC" .
9/7 Add T stats to alt rooms 169 and 171 .
9/8 Det Z]/] l add isolation valves to all auto air vents .
10/2 Move lights east in Boiler room to clear HWH stack.
10/5 Provide power for CUH-11 on west wall .
Move power and score-board jacks from center of gym floor to
center of bleachers.
10/8 Move score-board jacks from center of gym floor to center of
bleachers. Add cable TV outlets and 2 phone jacks (two
separate lines) at center of gym bleachers.
tor
® Move phone to south wall of corridor 104 as per 2/2 and 2/5.
Move heat detector on North end of Boiler rm to East 4 ' to
clear HWH stack.
Spec changes:
Section 06100
Pg 7 Par 3 . 02 (A) Blocking required at but not limited to
the following locations:
1. Tack/Chalk boards
2 . Wall mounted door stops
3 . Door mag' s on fire doors
4 . Towel and toilet paper dispensers
5 . Toilet partition wall brackets
6 . TV wall mount brackets
7 . Hand rails
8 . Damper motors and actuators
Section 08710
Pg 4 Par 2 . 03 Add heavy weight ball bearing five knuckle
hinges only. Delete old three knuckle hinge.
Pg 5 Par 2 . 06 (C) Delete 15C. Use 9K cylindrical locksets .
Delete Mortise locksets.
Section 11500
Pg 6 Par 2 . 04 (A) All KIBSD scoreboards are Daktronics.
Boards to be configured for basketball as primary display
with volleyball and wrestling as auxiliary display. Prefer
DAK Model BB-1713S or BB-1813S with optional protective
screens installed.
Section 15484
Ak
Pg 3 Par 1 . 09 (A) Change to read "Furnish to the owner, two
extra fuel filters of each size used. " Delete (B)
Section 15515
Pg 5 Par 3 . 01 Add (M) Provide manual isolation valves for
all automatic air vents.
Section 15835
Pg 4 Par 2 . 04 (B) Change easily removed panel to hinged
cover.
Section 15985
Pg 8 Par 3 . 10 (C) 1 . Change to read "Day and Night Mode of
Operation will be controlled by DDC Controller internal
clock. "
Pg 9 Par 3 . 11 (C) 1 . Change to read "Day and Night Mode of
Operation will be controlled by DDC controller internal
clock. "
Section 16535
Pg 1 Par 2 . 02 Add (K) Provide wire guards in gym and
commons.
Pg 2 Par 2 . 04 Add (C) Provide wire guards in Gym, corridors
104 , 120 and Alt Corridor 174 .
Section 16721
Pg 5 Par 2 . 03
a. Add corridors 104 , 120 and Alt corridor 174
b. Add guards for detectors installed in bathroom
105 , 106,vest. 119 and alt vest 172
c. Add guards for detectors installed in corridors
104 , 120, Alt corridor 174 and commons
d. Add guards in gym.
Section 16726
Pg 3 Par 2 . 03 (A) add guards for detectors in corridors
104 , 120,gym, Alt corridor 174 and commons .
ADD GUARDS FOR ALL TSTATS, TEMP TRANSMITTERS AND OTHER SENSORS
LOCATED IN CORRIDORS, VEST, COMMONS, BATHROOM AND GYM.
Bonney-Specs
03310 Cold weather concrete and roof
05210 Same as 05120 Quality Control
05310 Steel deck - Needs a contractor representative to inspect
on a regular basis
06200 Screw fasteners
07600 Keep recovery board dry
08331 Need drop time test on overhead door
The satellite dish placement was discussed and the top of the gym
was thought to be the best place for it.
Mr. Bonney spoke about his concern of the schedule being so fast
tracked. He said that looking at the Northstar prints as they
stand with this schedule, professionally, it would take his
entire efforts in order to match the schedule. His concerns were
that the roof was going to be installed during the cold winter
months and that would create more problems. Mr. Smith suggested
that they add an alternative bid schedule for possibly adding 90
days to the project. He stated that it is a six million dollar
al project being done in one year, and that anywhere else in the
country much more time would be given to do it. He asked Mrs.
Walters if moving in after the Christmas break would create a
problem. Mrs . Walters stated that it definitely would, and that
they could not wait. She also said that everyone knew going into
this project that time was going to be an issue. Mr. Koning
asked if the project could be done in the time frame allowed and
Mr. Smith stated that it could. Mr. Bonney replied that the
project will need to be managed very closely by the Borough and
will take more manpower. Mr. Koning asked if Mr. Bonney would
beable to attend the assembly work session on July 28th to bring
this to their attention. Mr. Bonney stated he would attend.
VI. COMMENTS
Mr. Koning stated that the meeting scheduled for next Wed. , July
19 , 1994 is not necessary. If anyone has any other comments
about the plans, they can bring them in writing to the
Engineering office and they will FAX them to the architect. The
next meeting is scheduled for July 26, 1994 to approve the 95%
drawings of Northstar.
4
i3r
VII . ADJOURNMENT
Mr. Bonney moved to adjourn the meeting. Mr Schaffer seconded.
The meeting was adjourned by Mr. Koning at 10 . 20 p.m.